To ask the Secretary of State for Transport, what Directly Operated Railways’ total staffing budget was in each of the years since 2010-11; and what its planned staffing budget is for 2014-15 and 2015-16.

Stephen Hammond

The total budgeted staff costs for the years in question are as follows.

£000’s

Salaries

Other Staff Costs

Consultants

Total

2010/11

539

77

412

1028

2011/12

476

52

386

914

2012/13

194

32

853

1079

2013/14

378

10

455

843

2014/15

1245

61

187

1493

2015/16

No Budget

As with all other costs associated with Directly Operated Railways (DOR), these are recovered through a combination of a management charge to their subsidiary (East Coast Main Line Company Ltd), charges to the performance bond which was secured from National Express following the early termination of their franchise in 2009 and fees charged to the Department for Transport for services in connection with the Rail Franchising (Direct Awards) programme.

The total headcount in DOR for the years in question are set out in the table below.

Year ending March

Core DOR

Direct Award

2010

7

2011

7

2012

7

2013

8

2014

7

6*

*Prior to the year ending March 2014, DOR’s work in respect of the Direct Award programme was staffed by a combination of the core DOR team and consultants.