Speeches

Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

The below Parliamentary question was asked by Lilian Greenwood on 2015-12-17.

To ask the Secretary of State for Transport, whether the Gospel Oak to Barking Line electrification programme includes electrification of that line’s freight links.

Claire Perry

The Gospel Oak–Barking electrification programme includes plans to electrify the freight links. The timing and funding for these links is being reviewed in conjunction with Sir Peter Hendy’s re-plan of Network Rail enhancements and the revised cost estimates of all electrification projects. The main scheme continues to be on target for completion in 2017.