    The below Parliamentary question was asked by Jeremy Corbyn on 2014-06-12.

    To ask the Secretary of State for Defence, what facility rekit projects have taken place at the Atomic Weapons Establishment under the scope of the Nuclear Weapons Capability Sustainment Project; and what the cost of each such project was.

    Mr Philip Dunne

    The term rekit is used by the Atomic Weapons Establishment (AWE) to mean the replacement or modernisation of process plant and /or equipment within an existing facility, including upgrading of building services. The following is a list of major facility rekits that have or are taking place at AWE. There are also a number of more minor rekits underway which are not listed.

    Depleted Uranium Upgrade
    Beryllium Facility
    Plutonium Capability Programme (A90)
    Enriched Uranium Facility (A45)
    Explosive storage and processing Facility
    Salts Sustainment
    Facility for assembly/disassembly of Warhead

    The information relating to individual rekit costs for each facility for the years 2003 to date is not centrally held and could only be provided at disproportionate cost.

  • Andrew Percy – 2014 Parliamentary Question to the Department for Communities and Local Government

    Andrew Percy – 2014 Parliamentary Question to the Department for Communities and Local Government

    The below Parliamentary question was asked by Andrew Percy on 2014-04-08.

    To ask the Secretary of State for Communities and Local Government, what steps he is taking to encourage local authorities to improve mobile signal coverage in rural areas by permitting use of their land for mobile network base stations.

    Nick Boles

    Local authorities have an active role to play in mobile network deployment by assisting operators to find suitable land and structures. This is set out in the “Code of Best Practice on Mobile Network Development in England”, facilitated by Government, signed by operators, local authorities and other interested parties which was issued in July 2013. It is available at:

    http://www.mobilemastinfo.com/images/stories/2013_Code_of_best_practice/Code_of_Best_Practice_on_Mobile_Network_Development_-_Published_24-07-2013.pdf

    “

  • Kevan Jones – 2014 Parliamentary Question to the Ministry of Defence

    Kevan Jones – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Kevan Jones on 2014-06-12.

    To ask the Secretary of State for Defence, with reference to the National Audit Office report, Army 2020, HC 263, published on 11 June 2014, page 10, which Minister in his Department signed off on the decision not to provide supporting ICT infrastructure for Capita’s new recruitment software as part of his Department’s contractual arrangements with Capita in relation to the Recruiting Partnering Project.

    Anna Soubry

    I refer the hon. Member to the answer I gave on 21 January 2014 (Official Report, column 111W).

  • Madeleine Moon – 2014 Parliamentary Question to the Ministry of Defence

    Madeleine Moon – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Madeleine Moon on 2014-04-08.

    To ask the Secretary of State for Defence, pursuant to the Answer of 19 March 2014, Official Report, column 650W, on armed forces: disciplinary proceedings, how many and what amount of ex gratia payments were made to armed forces personnel incorrectly disciplined following receipt of a police caution; and if he will make a statement.

    Anna Soubry

    No such ex-gratia payments have been made.

  • Madeleine Moon – 2014 Parliamentary Question to the Ministry of Defence

    Madeleine Moon – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Madeleine Moon on 2014-06-12.

    To ask the Secretary of State for Defence, how many (a) male and (b) female recruits dropped out of training at Catterick Infantry Training Centre before completing Phase 1 in each year since 2006; how many such recruits in each category were aged under 18 when they enlisted; and if he will make a statement.

    Anna Soubry

    Infantry training at Catterick is comprised of the Combat Infantryman’s Course, which is a combined phase one and phase two course. For this reason it is not possible to provide the information requested for those who dropped out of training before completing Phase 1. The table shows all those who failed to complete the Combat Infantryman’s Course.

    No female recruits undergo infantry training and therefore figures shown relate to males only:

    Year

    Discharged at ITC (Male)

    Under 18 on entry (Male)

    2006-07

    950

    320

    2007-08

    1,090

    290

    2008-09

    1,060

    210

    2009-10

    1,400

    250

    2010-11

    840

    90

    2011-12

    1,260

    120

    2012-13

    910

    100

    2013-14

    680

    80

    Figures have been rounded to 10; numbers ending in ‘5′ are rounded to the nearest multiple of 20 to prevent systematic bias.

  • Mark Tami – 2014 Parliamentary Question to the Department for Energy and Climate Change

    Mark Tami – 2014 Parliamentary Question to the Department for Energy and Climate Change

    The below Parliamentary question was asked by Mark Tami on 2014-04-08.

    To ask the Secretary of State for Energy and Climate Change, what the estimated value of the contract of Dounreay Site Restoration was at the time of the award in April 2012; what the estimated savings to the public purse were; what the estimated value of the contract is to date; and what the estimated savings to the public purse are to date.

    Michael Fallon

    The estimated Target Cost at the time of contract award in 2012 was approximately £1.5 billion in 2012/13 money values. It covered all of the scope in the Dounreay Lifetime Plan to bring the site to its Interim End State which was capable of definition at the time of tender; it excluded scope that was not capable of definition at the bid stage. The contract contained provisions for change control for new scope and also for indexation for inflation. The Target Cost at 31 March 2014 is £ 1.7bn. The estimated saving to the public purse arising from the Preferred Bidder’s target costs compared to the extant Lifetime Plan was, and remains, well in excess of £1 billion.

  • Lord Stoddart of Swindon – 2014 Parliamentary Question to the Foreign and Commonwealth Office

    Lord Stoddart of Swindon – 2014 Parliamentary Question to the Foreign and Commonwealth Office

    The below Parliamentary question was asked by Lord Stoddart of Swindon on 2014-06-18.

    To ask Her Majesty’s Government, further to the Written Statement by Baroness Warsi on 17 June (WS 586–88), whether they plan to abandon their demand that President Assad step down and to urge co-operation between his government and the official opposition to defeat the Islamic State of Iraq and ash-Sham and other Islamic terrorist groups in Syria.

    Baroness Warsi

    The Assad regime is the primary cause of terrorism in Syria, not the solution to it. The most effective way to tackle terrorism in Syria is to support the moderate opposition in its efforts to protect the Syrian people from the twin threats of tyranny and terrorism. The only sustainable solution to the crisis in Syria is to reach a negotiated political transition by the mutual consent of both sides – this is the principle in the Geneva Communiqué as endorsed by the UN Security Council.

  • Maria Eagle – 2014 Parliamentary Question to the Department for Environment, Food and Rural Affairs

    Maria Eagle – 2014 Parliamentary Question to the Department for Environment, Food and Rural Affairs

    The below Parliamentary question was asked by Maria Eagle on 2014-04-08.

    To ask the Secretary of State for Environment, Food and Rural Affairs, whether the additional £5 million for tackling waste crime announced in the budget statement will reduce in the planned workforce and associated workload in the enforcement and legal department of the Environment Agency.

    Dan Rogerson

    Defra and the Environment Agency have been working together to ensure that the additional funding is targeted effectively to tackle waste crime. A decision on how the additional £5 million will be spent is subject to Defra Ministerial approval.

    Depending on how the £5 million is to be spent, the Environment Agency will review its planning assumptions to determine the impact on its workforce and associated workload

  • Gregory Campbell – 2014 Parliamentary Question to the Department for Business, Innovation and Skills

    Gregory Campbell – 2014 Parliamentary Question to the Department for Business, Innovation and Skills

    The below Parliamentary question was asked by Gregory Campbell on 2014-06-18.

    To ask the Secretary of State for Business, Innovation and Skills, how many premium rate type telephone lines were in use for members of the public to contact his Department in (a) June 2010 and (b) June 2014.

    Jenny Willott

    The Department had no public facing premium rate lines in use in June 2010 or June 2014.

  • Barry Gardiner – 2014 Parliamentary Question to the Department for Environment, Food and Rural Affairs

    Barry Gardiner – 2014 Parliamentary Question to the Department for Environment, Food and Rural Affairs

    The below Parliamentary question was asked by Barry Gardiner on 2014-04-08.

    To ask the Secretary of State for Environment, Food and Rural Affairs, by what date each of the 40 air quality zones with exceedances of nitrogen dioxide limit values in 2010 will achieve compliance with 2010 nitrogen dioxide limit values.

    Dan Rogerson

    Meeting EU standards for nitrogen dioxide remains a challenge for many large urban areas in the UK and across Europe. In 2011 Defra submitted estimates of the year each part of the UK would meet these standards to the European Commission. The assumptions behind our projections are regularly reviewed to reflect new understanding and we expect to have new projections available later this year.