Tag: Lilian Greenwood

  • Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Lilian Greenwood on 2016-04-29.

    To ask the Secretary of State for Transport, at which stations Network Rail plans to defer Access to All works from Control Period 5 into Control Period 6.

    Claire Perry

    The Access for All programme was‎ reviewed as part of Sir Peter Hendy’s report into Network Rail’s investment programme for Control Period 5 (2014-2019).

    We are currently considering consultation responses to the report and working with Network Rail to decide which stations may be affected.

  • Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Lilian Greenwood on 2016-05-09.

    To ask the Secretary of State for Transport, pursuant to the Answer of 28 April 2016 to Question 34946, what the recent meetings held by Ministers and officials of his Department with the motor insurance industry were that were referred to in that Answer and what was discussed at those meetings; and how many meetings he has held with personal injury law firms in the same time period and what was discussed at those meetings.

    Andrew Jones

    I last met with representatives from across the insurance industry on 14 January to discuss a range of issues. These included young driver safety and technology measures which can reduce the cost of insurance and thus reduce incentives to drive without insurance and the implications of a European Court of Justice Judgment on the scope of compulsory motor insurance. In addition I met with the British Insurance Brokers’ Association last summer, shortly after my appointment.

    My officials have regular meetings with representatives from the insurance industry. At these a range of issues have been discussed including young driver safety and technology such as telematics, uninsured driving, the scope of compulsory motor insurance, and driverless cars. Representatives of some parts of that industry have raised with us the issue of Insurance Premium Tax; this is a matter for the Chancellor of the Exchequer.

    There have been no recent meetings with personal injury law firms regarding motor insurance.

  • Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Lilian Greenwood on 2016-05-25.

    To ask the Secretary of State for Transport, what estimate he has made of the number of uninsured vehicles in the UK; and how many vehicles were seized for unpaid insurance in each year since 2009-10.

    Andrew Jones

    Since 2011 the Government has had in place an insurance and compliance strategy, namely the Continuous Insurance Enforcement (CIE) scheme operated by DVLA and the Motor Insurers Bureau, which aims to reduce the level of uninsured driving.

    It is estimated that CIE has already helped reduce levels of uninsured driving from 1.4 million in 2010 to 1 million vehicles now.

    The police have powers under Section 165A of the Road Traffic Act 1988 to seize a vehicle that is being used on a public road without motor insurance. How police enforce the law is an operational matter for their discretion.

    The table below shows the number of vehicles seized by the police for driving without insurance.

    Year

    2009

    2010

    2011

    2012

    2013

    2014

    2015

    vehicles seized

    180,000

    150,000

    140,000

    137,000

    135,000

    116,000

    121,000

  • Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Lilian Greenwood on 2016-06-13.

    To ask the Secretary of State for Transport, pursuant to the Answer of 9 June 2016 to Question 39519, what the whole life cost of the East Coast Main Line Intercity Express fleet is; and how much of that cost will be met by funding from his Department.

    Claire Perry

    Whole life costs of the East Coast Main Line fleet are part of the £2.7bn investment for the Intercity Express Programme East Coast which includes the design, finance and maintenance of the rolling stock and maintenance facilities over the 27.5 year term. It is not possible to break this cost down further.

    The Departments costs in support of this investment are supported through funding of infrastructure enhancements and agreement in the East Coast Franchise Agreements to ensure the benefits of the IEP trains are delivered.

  • Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Lilian Greenwood on 2016-06-27.

    To ask the Secretary of State for Transport, pursuant to the Answer of 13 June 2016 to Question 39847, on travel, when he plans to update the National Transport Model estimates given in that Answer to take account of the potential effects of the cycling and walking investment strategy.

    Andrew Jones

    We plan to update the National Transport Model with the impacts of the cycling and walking investment strategy once we have more complete information on the national impact of local cycling and walking strategies later in the year.

  • Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Lilian Greenwood on 2016-07-20.

    To ask the Secretary of State for Transport, pursuant to the Answer of 9 May 2016 to Question 36626, what contributions he expects the Local Enterprise Partnerships to make towards the cost of the Market Harborough straightening works.

    Paul Maynard

    The Local Enterprise Partnerships are planning to contribute £13 million from Local Growth Deals as part of this government’s record investment in the rail network.

  • Lilian Greenwood – 2015 Parliamentary Question to the Department for Transport

    Lilian Greenwood – 2015 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Lilian Greenwood on 2015-11-02.

    To ask the Secretary of State for Transport, pursuant to the Answer of 29 October 2015 to Question 13286, whether any additional projects have been paused but not announced by Network Rail.

    Claire Perry

    The Secretary of State announced on 25 June 2015 the pause of work on Midland Main Line electrification and TransPennine electrification. This was to avoid potentially abortive costs while work was carried out to replan the delivery of these projects. On 30 September 2015 work on these projects resumed.

    Other Network Rail Control Period 5 projects have been continuing while Sir Peter Hendy carries out his review.

  • Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Lilian Greenwood on 2015-12-17.

    To ask the Secretary of State for Transport, when he expects Network Rail’s review of the delivery programme of the Great Western Main Line electrification to be completed.

    Claire Perry

    Network Rail’s review of the delivery programme of the Great Western Main Line electrification has been completed as part of the Hendy review and details will be included in the Enhancement Delivery Plan update to be published in early 2016.

  • Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Lilian Greenwood on 2016-01-18.

    To ask the Secretary of State for Transport, which Highways England capital programme schemes are behind schedule.

    Andrew Jones

    Progress is being made on all the major schemes listed in Highways England’s Delivery Plan and it is on track by the end of March 2016 to have started construction on 5 schemes and opened 5 schemes – all scheduled to start or open in 2015/16. Naturally, within this significant £15 billion investment programme of 112 schemes within the current road period, a small minority of schemes may occasionally experience variations in timescale or in the precise form of the solution.

    In particular there are two schemes where the schedule has been revised.

    For A63 Castle Street progress of the main scheme has been delayed in order to investigate more fully the environmental impacts caused by the scheme and how these can be best mitigated. However, the construction of Princes Quay footbridge is on track to begin in April. My Rt Hon Friend the Secretary of State has also kept the Rt Hon Member for Kingston upon Hull West and Hessle (Alan Johnson MP), in whose constituency this scheme is, regularly appraised of the relevant issues.

    After considering responses to the recent public consultation for the M54 / M6 / M6 Toll, an announcement of the preferred route has been delayed in order to allow a reappraisal of the options.

  • Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    Lilian Greenwood – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Lilian Greenwood on 2016-02-02.

    To ask the Secretary of State for Transport, pursuant to the Answer of 5 November 2015 to Question 14462, what the benefit: cost ratio was of the Great Western Main Line electrification programme on the latest date for which figures are available.

    Claire Perry

    Network Rail is continuing to refine its work schedule for delivering the Great Western Route Modernisation programme and the Hendy Report is currently the subject of a consultation with stakeholders. A revised benefit-cost ratio for the programme will be produced after the conclusion of these important strands of work.