Speeches

Madeleine Moon – 2016 Parliamentary Question to the Ministry of Defence

The below Parliamentary question was asked by Madeleine Moon on 2016-01-13.

To ask the Secretary of State for Defence, how many Hunter Class mine countermeasures vessels have completed their re-engineering; when he expects all eight to be completed; and if he will make a statement.

Mr Philip Dunne

To date, work to replace the propulsion system on four of the Hunt Class mine countermeasures vessels has been completed with the fifth due for completion later this year. Due to changes applied to the ships upkeep programme combined with the need to address emerging engineering issues, work on the remaining three vessels is now scheduled for completion by late 2019.