The below Parliamentary question was asked by Lord Bradshaw on 2014-03-13.

To ask Her Majesty’s Government, in the light of their plans to introduce new electrified railway lines between Manchester and Liverpool in December, whether they have taken into account the availability of electric trains as part of their negotiations to procure rolling stock.

Baroness Kramer

As announced today (27 March) the Department for Transport has granted a Direct Award to Northern for 22 months and is working with them to ensure rolling stock is available for a phased rollout of electric services between Liverpool and Manchester from the December 2014 timetable.

The Department takes account of availability of electric rolling stock in its decisions and the stock for this route will be modern, cascaded stock from other routes.