To ask the Secretary of State for Transport, what progress has been made on the electrification works on the Manchester to Stalybridge railway line.

Paul Maynard

The electrification works on the railway line between Manchester and Stalybridge (Phase 5 of the North West Electrification Programme), due by December 2017 will see the installation of infrastructure and improvements to facilitate overhead electrification of the railway line, delivering journey time benefits for passengers in the north of England.

Good progress has been made on the design and planning aspects of the project. Canopy works at Stalybridge station have been completed to achieve high level clearance required for electrification, and track interventions have taken place on Phase 5 infrastructure, including track lowering and renewals to enable electrification. Detailed Design is progressing well and is at an advanced stage of development.

This is an extremely complex engineering project ensuring electrification is delivered alongside capacity and journey time improvements. Network Rail continue to work with their contractors to develop a delivery programme to maximise passenger benefits and minimise disruption to a busy passenger and freight rail corridor.