Jamie Reed – 2016 Parliamentary Question to the Department for Energy and Climate Change

The below Parliamentary question was asked by Jamie Reed on 2016-04-27.

To ask the Secretary of State for Energy and Climate Change, when she expects the regulatory approval processes, including the Generic Design Assessment, to be completed for proposed new nuclear reactors at Wylfa in Wales.

Andrea Leadsom

The regulatory approval process for new nuclear reactors proposed for construction in the UK is run by the UK’s independent nuclear regulators, the Office for Nuclear Regulation (ONR), the Environment Agency (EA) and Natural Resources Wales (NRW). DECC does not direct or intervene in the assessment process.

Generic Design Assessment of the ABWR reactor proposed for construction at the Wylfa site in Wales is targeted for completion in Q4 2017. Horizon has not yet made applications for site specific regulatory approvals, such as licensing and environmental permits, but DECC expects these to be made in good time, targeting completion for 2018.