Tag: Clive Efford

  • Clive Efford – 2016 Parliamentary Question to the Department of Health

    Clive Efford – 2016 Parliamentary Question to the Department of Health

    The below Parliamentary question was asked by Clive Efford on 2016-10-11.

    To ask the Secretary of State for Health, what discussions he has had with Greenwich Clinical Commissioning Group on the future of the Fracture Clinic Service and physiotherapy service in Greenwich and whether that service is included in the contract awarded to Circle Holdings PLC to provide musculoskeletal services; and if he will make a statement.

    Mr Philip Dunne

    The provision of local health services is a matter for the local National Health Service.

    There have been no meetings between Ministers at the Department of Health and Greenwich Clinical Commissioning Group (CCG) on progress towards meeting the Getting it Right First Time requirements since the contract for musculoskeletal services was awarded to Circle Holdings PLC.

    Neither have there been meetings between Ministers at the Department and Greenwich CCG regarding the future of the Fracture Clinic Service and physiotherapy service in Greenwich and on whether the service is included in the contract awarded to Circle Holdings PLC to provide musculoskeletal services.

  • Clive Efford – 2016 Parliamentary Question to the Department for Transport

    Clive Efford – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Clive Efford on 2016-01-21.

    To ask the Secretary of State for Transport, pursuant to the Answer of 19 January 2016 to Question 22573, what equipment and buildings of any kind situated along the side of the Bexleyheath rail line were damaged in the landslides which blocked the line during the week beginning 11 January 2016; and if he will make a statement.

    Claire Perry

    Network Rail has advised that a signalling control cabinet was pushed over by the recent landslip at Barnehurst, and then had to be moved to a location away from the affected area to enable access to temporarily stabilise the landslide. This involved moving the staging on which the cabinet was sited, the cabinet itself, and the cables.

    Network Rail further advises that the earthwork was last examined on 5 February 2015, when its condition showed no signs of impending failure. Its condition prior to the earthworks failure was such that its next inspection would have been three years from that date.

  • Clive Efford – 2016 Parliamentary Question to the Department of Health

    Clive Efford – 2016 Parliamentary Question to the Department of Health

    The below Parliamentary question was asked by Clive Efford on 2016-09-02.

    To ask the Secretary of State for Health, what the role of Numis Securities is in the bidding process for the musculoskeletal service in Greenwich; what funding has been paid to that company relating to that role; and if he will make a statement.

    Mr Philip Dunne

    The procurement of local health services by means of competitive tendering is a matter for the local National Health Service.

    However, we are advised that NHS Greenwich Clinical Commissioning Group has not had any involvement with Numis Securities during the process leading to the recent award to Circle Health of the contract for the provision of musculoskeletal services in Greenwich.

  • Clive Efford – 2016 Parliamentary Question to the Department of Health

    Clive Efford – 2016 Parliamentary Question to the Department of Health

    The below Parliamentary question was asked by Clive Efford on 2016-10-11.

    To ask the Secretary of State for Health, what discussions he has had with Lewisham and Greenwich Healthcare Trust on progress towards meeting the Getting it Right First Time requirements since the contract for musculoskeletal services was awarded to Circle Holdings PLC; and if he will make a statement.

    Mr Philip Dunne

    The provision of local health services is a matter for the local National Health Service.

    There have been no meetings between Ministers at the Department of Health and Greenwich Clinical Commissioning Group (CCG) on progress towards meeting the Getting it Right First Time requirements since the contract for musculoskeletal services was awarded to Circle Holdings PLC.

    Neither have there been meetings between Ministers at the Department and Greenwich CCG regarding the future of the Fracture Clinic Service and physiotherapy service in Greenwich and on whether the service is included in the contract awarded to Circle Holdings PLC to provide musculoskeletal services.

  • Clive Efford – 2015 Parliamentary Question to the Department for Culture, Media and Sport

    Clive Efford – 2015 Parliamentary Question to the Department for Culture, Media and Sport

    The below Parliamentary question was asked by Clive Efford on 2015-11-09.

    To ask the Secretary of State for Culture, Media and Sport, what assessment he has made of the financial effect on the Horserace Levy Scheme of betting operators locating their online services off-shore; and if he will make a statement.

    Tracey Crouch

    The Government remains committed to replacing the current levy system to create a level playing field for British based and offshore gambling operators.

  • Clive Efford – 2016 Parliamentary Question to the Department for Transport

    Clive Efford – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Clive Efford on 2016-01-21.

    To ask the Secretary of State for Transport, pursuant to the Answer of 19 January 2016 to Question 22575, whether failure to inspect equipment or buildings situated adjacent to Bexleyheath rail line contributed to the line being blocked during the week beginning 11 January 2016; and if he will make a statement.

    Claire Perry

    Network Rail has advised that a signalling control cabinet was pushed over by the recent landslip at Barnehurst, and then had to be moved to a location away from the affected area to enable access to temporarily stabilise the landslide. This involved moving the staging on which the cabinet was sited, the cabinet itself, and the cables.

    Network Rail further advises that the earthwork was last examined on 5 February 2015, when its condition showed no signs of impending failure. Its condition prior to the earthworks failure was such that its next inspection would have been three years from that date.

  • Clive Efford – 2016 Parliamentary Question to the Department of Health

    Clive Efford – 2016 Parliamentary Question to the Department of Health

    The below Parliamentary question was asked by Clive Efford on 2016-09-02.

    To ask the Secretary of State for Health, how his Department consulted local GPs and other health providers during the tendering process for musculoskeletal services in Greenwich; how his Department assessed the implications of the outcome of that process for the services provided by those people; and if he will make a statement.

    Mr Philip Dunne

    The procurement of local health services by means of competitive tendering is a matter for the local National Health Service.

    We are advised that NHS Greenwich Clinical Commissioning Group (CCG) undertook a review of the provision of musculoskeletal (MSK) services in the area in 2014, involving local general practitioners (GPs), secondary care clinicians, other MSK clinicians and patient groups. The CCG took account of this exercise in confirming its commissioning intentions for an integrated MSK service pathway. The CCG subsequently held a GP clinical commissioner-led provider engagement event on 2 March 2016 to seek feedback on the clinical service specification and the proposed contractual model.

    We understand that, as part of the procurement process, the MSK Programme Board was fully apprised of the Our Healthier South East London initiative, the predecessor to the Sustainability and Transformation Plan (STP) in respect of elective orthopaedic centres.

    We are advised that the Invitation to Tender (ITT) developed as part of the procurement exercise explicitly stated the aspirations of these two initiatives, in addition to the proposed implementation timeline. When submitting their bids, all prospective providers were required to confirm their understanding and acceptance of the planned new model of in-patient care. Patient choice continues to apply with regard to both this local procurement and the South East London STP proposals on elective care centres.

    We understand that the ITT issued to potential service providers, was divided into sections, with each section allocated a weighting. The financial weighting was designed to ensure that the selection of the preferred provider was driven by clinical quality scores whilst remaining within the CCG’s published financial envelope. The detailed clinical service specification will be used to hold the provider to account within the format of the NHS national standard contract.

    Health Ministers have not received any representations from local health practitioners in Greenwich with regard to the provision of MSK services in the area.

  • Clive Efford – 2016 Parliamentary Question to the Department of Health

    Clive Efford – 2016 Parliamentary Question to the Department of Health

    The below Parliamentary question was asked by Clive Efford on 2016-10-17.

    To ask the Secretary of State for Health, whether he has received representations on whether Greenwich Clinical Commissioning Group was quorate at its meeting of 29 June 2016 when it awarded the contract for musculoskeletal services to Circle Holdings PLC; and if he will make a statement.

    Mr Philip Dunne

    The procurement of local health services by means of competitive tendering is a matter for the local National Health Service.

    The Department has not received any representations on the matter of whether Greenwich Clinical Commissioning Group (CCG) was quorate at its meeting of 29 June 2016 when it awarded the contract for musculoskeletal services to Circle Health.

    We are informed by NHS England that the CCG follows standard NHS procurement procedures and these procedures were followed for this procurement.

  • Clive Efford – 2015 Parliamentary Question to the Department for Culture, Media and Sport

    Clive Efford – 2015 Parliamentary Question to the Department for Culture, Media and Sport

    The below Parliamentary question was asked by Clive Efford on 2015-11-09.

    To ask the Secretary of State for Culture, Media and Sport, what progress his Department has made on plans to introduce a Horserace Betting Right; and if he will make a statement.

    Tracey Crouch

    Work is continuing on the detailed policy design of the Horserace Betting Right. We will make an announcement in due course.

  • Clive Efford – 2016 Parliamentary Question to the Department for Transport

    Clive Efford – 2016 Parliamentary Question to the Department for Transport

    The below Parliamentary question was asked by Clive Efford on 2016-01-21.

    To ask the Secretary of State for Transport, pursuant to the Answer of 19 January 2016 to Question 22574, for what reasons, during the closure of the Bexleyheath rail line during the week beginning 11 January 2016, (a) Southeastern services on adjacent lines were cancelled, (b) there was a lack of information about alternative services and (c) staff had no information to pass onto customers about alternative services or when replacement bus services would arrive; what systems were put in place to communicate regular updates of information to staff so customers could be given accurate advice; what advice was given to staff regarding assistance for people with disabilities; what steps he is taking to determine whether the responses to the situation from Network Rail and Southeastern were adequate; and if he will make a statement.

    Claire Perry

    Following the unfortunate landslip at Barnehust, it was necessary to close the line serving Bexleyheath in order that repairs could be carried out.

    As a result of the Bexleyheath line closure, Southeastern have had to run more trains on the adjacent lines to provide extra capacity for passengers. This led to minimal cancellations to the scheduled timetable on adjacent lines.

    Information regarding alternative travel arrangements was provided by posters at affected stations, station announcements, on National Rail Industry systems, the Southeastern website and on social media.

    Staff were given regular updates on the alternative travel arrangements and station announcements were made where appropriate. Replacement buses were in operation between Lewisham and Dartford via Bexleyheath in both directions. Other bus services were accepting Southeastern tickets, additionally, Docklands Light Railway and London Underground were accepting tickets where appropriate. Regular updates were provided to station management, who provided briefings to their station staff. The Passenger Assist service was in effect and Southeastern staff were advised to book taxis from stations that were not accessible for those passengers who required them.

    My officials were in regular contact with Southeastern and Network Rail, who ensured that the line was opened as quickly as possible and that passengers were kept informed at all times.