The below Parliamentary question was asked by Caroline Lucas on 2015-12-15.
To ask the Secretary of State for Defence, with reference to the Answer of 2 July 2014, Official Report, column 676W on AWE, what his most recent estimate is of the (a) anticipated out-turn cost and (b) projected in-service date of each of the new build projects in the Atomic Weapons Establishment Site Development Context Plan.
Michael Fallon
The approved costs and in-service dates of the current new build projects at the Atomic Weapons Establishment, are shown below.
In-service dates are shown in bandings to avoid prejudice to national security and defence. No costs are attributed to projects detailed in Table 2 as these have yet to be formally approved.
Table 1 – Approved new-build projects
|
Ongoing projects
|
Function
|
In-Service Period
|
Approved cost £million
|
|
Warhead assembly/disassembly – Mensa
|
Manufacturing/production
|
2016-20
|
734
|
|
Uranium components – Pegasus
|
Manufacturing/production
|
2016-20
|
634
|
Table 2 – Planned projects not yet approved
|
Ongoing projects
|
Function
|
In-Service Period
|
|
Salts Processing – Octans
|
Testing/research
|
2020-25
|
|
Initiator system manufacture-Taurus
|
Manufacturing/production
|
2020-25
|
|
Large Scale formulations-Scorpius
|
Manufacturing/production
|
2025-30
|
|
Small Scale formulations-Cepheus
|
Manufacturing/production
|
2025-30
|
|
New Plutonium (Pu) Facility – not yet named
|
Manufacturing/production
|
2025-30
|
|
New depleted Uranium Facility
|
Manufacturing/production
|
2025-30
|
|
Assembly for Trials-Columba
|
Testing/research
|
2025-30
|
|
High Explosive Climatic Trials
|
Testing/research
|
2025-30
|
|
Non-Metallics & materials R&D-Libra
|
Testing/research
|
2025-30
|
|
Chemical processing-Astra
|
Manufacturing/production
|
2025-30
|