Tag: Strategic Rail Authority

  • HISTORIC PRESS RELEASE : Strategic Rail Plan – Briefing note for the North East [January 2002]

    HISTORIC PRESS RELEASE : Strategic Rail Plan – Briefing note for the North East [January 2002]

    The press release issued by the Strategic Rail Authority on 14 January 2002.

    Briefing note for the North East

    (the area covered by Govt. Office for the North East – Northumberland, Tyne & Wear, Durham, Darlington, Hartlepool, Middlesbrough, Redcar and Cleveland and Stockton-on-Tees)

    Objectives of the Strategic Plan

    The Plan sets out how the SRA intends to tackle the rail industry’s problems and priorities in the short, medium and long term to:

    • restore stability in the industry, allowing performance to improve;
    • deliver growth to meet the 10 Year Plan core targets of:
    • 50% increase in passenger kilometres
    • reduction in overcrowding which breaches the SRA’s standards
    • 80% increase in freight tonne-kilometres
    • build a pipeline of projects at different stages of development against which contractors and suppliers can plan.

    The plan also meets where possible SRA’s other priorities set by Government, including better integration with other transport modes, expansion of capacity and promotion of the use of the railway network.

    The priorities have been developed taking into account dialogue with the Rail Passengers’ Committee for North East England, the Association of North East Councils and One NorthEast (the regional assembly and RDA), Government Office for the North East and local authorities within the region.

    The SRA contributed to the preparation of Regional Planning Guidance for the North East which is expected to be issued in early 2002, as well as the preparation of the RTS currently underway.

    The SRA has participated in the following Multi Modal Studies (MMS):

    • Tyneside Area Multi Modal Study (TAMMS)
    • A1 North of Newcastle.

    National schemes with benefits for the North East region

    • Train Protection and Warning Systems
    • A Company Neutral Revenue Support schemes to be introduced in 2002 for intermodal and ‘less than trainload’ markets
    • Freight Facility Grants
    • Freight Small Schemes Fund
    • Incremental Outputs statements for track and signalling and stations
    • Rail Passenger Partnership Fund
    • Training through a National Rail Academy
    • National Rail Performance Fund to improve reliability of services
    • Proposals for a National Test Track to prove new rolling stock, before it is tested on the Railtrack network.
    • A programme of improvements for passengers with disabilities to improve station access and special training for staff.

    PRINCIPAL PROJECTS FOR THE NORTH EAST

    Developments 2001-2002

    Service developments

    • The Railtrack-Nexus PPP is to deliver the Sunderland Direct extension of the Tyne and Wear metro, with funding contributions from DTLR and the European Regional Development Fund:
    • full opening is on course for March 2002, South Hylton extension earlier
    • full Metro service Sunderland-Newcastle, plus two heavy rail expresses per hour
    • rolling stock freed for other duties
    • improvements to Sunderland station
    • 4.5km of new railway
    • extended integrated ticketing (Metro, bus and rail) in the Newcastle area.

    Rolling stock

    • 34 four-car CrossCountry Voyager trains to replace all loco-hauled services by May 2002. Progressive introduction of new trains during Autumn/Winter 2001/02, delivering extra services and greater reliability. Testing of first of 44 tilting five-car Super Voyager trains, which will deliver faster journey times.

    Performance improvements

    • Draft enforcement order made against Arriva Trains North, and further incentives put in place, to restore and improve train services.

     

    RPP proposals

    The following RPP proposals are currently being assessed:

    RPP proposal Status Output
    Ashington, Blyth and Tyne pre-qualification 2 trains per hour between Newcastle Central and Ashington Central, calling at Bedlington, Newsham and Backworth
    Leamside Lane pre-qualification re-opening of the Leamside line with three new stations
    Durham Coast Line – Phase II pre-qualification four new stations and the extension of half-hourly services beyond Hartlepool to Middlesbrough
    Tees-Tyne Express pre-qualification direct service between Middlesbrough and Newcastle with a journey time of less then one hour

     

     

     

    IOS stations

    ATN has 49 stations eligible for upgrading to provide modern facilities. All works are due to be completed by the end of 2004.

    IOS infrastructure in the North East

    The SRA is supporting, subject to value for money tests, the following incremental improvements to the network:

    IOS infrastructure scheme Main output Key requirement Expected completion date
    Sunderland to Middlesbrough capacity fast service achieved by extension of existing Hartlepool service to Middlesbrough 2005 – 06
    Newcastle to Carlisle capacity provision of a new turnback and bay platform at Hexham, and associated works, to allow additional services 2006 – 07

    Short Term Developments 2002-2005

    Service developments

    • CrossCountry: frequencies increased from summer 2003 timetable on core routes, to approximately double the present frequencies, with standard ‘clock face’ timetables and shorter journey times

    Rolling stock

    • Extension of ATN’s franchise to February 2003 brought a commitment to procure eighteen additional vehicles.

    Franchise negotiations

    SRA is negotiating a 2 year franchise extension with GNER to 2005, and details will be announced shortly. Essential requirements include:

    • additional incentives for improved operational performance and customer satisfaction
    • interior refurbishment of all existing IC225 and HST trains
    • a programme of HST reliability modifications
    • station improvements.

    TransPennine Express: in September 2001, the SRA was requested by Secretary of State to proceed towards the final stage of the letting of this franchise. Formal consultations with the 5 PTEs, which have the statutory right to specify services in their respective regions, were completed last year. 3 shortlisted counterparties will shortly be invited to submit revised proposals, taking into consideration any additional requirements emerging from the consultation process. It is intended that the new franchise will be awarded later this year, to commence early next year. The new franchise will look at opportunities for new rolling stock and depot facilities; more frequent express services on key routes; and addition of new destinations to the TPE network.

    Northern franchise

    The present North East franchise operated by ATN, which expires in February 2003, will be grouped with the North Western franchise, and a new Northern franchise created, with separate business units to improve local accountability; expressions of interest in the new franchise have been invited, and tendering will occur early this year. TransPennine Express will be separated from the services currently run by ATN and First North Western.

    Stations and passenger facilities

    • RPP-funded improved passenger information at stations between Hexham and Carlisle.
    • The SRA is funding 462 additional cycle parking spaces at 21 railway stations throughout the Tees Valley area.

    Infrastructure enhancements

    • Completion of CrossCountry infrastructure upgrade works at bottlenecks.
    • SRA is procuring design feasibility studies for further elements of the ECML upgrade and plans to lead a Joint Venture company that will deliver an upgrade of passenger and freight capacity on the ECML. Improvements could include:
    • longer trains and platforms
    • remodelling of Peterborough station
    • development of alternative freight lines to provide increased and segregated capacity between:
      • Peterborough and Doncaster via Lincoln
      • Doncaster and York
      • Northallerton and Ferryhill via Teeside
      • Newcastle and Edinburgh, through provision of freight loops
    • new bridge to take East-West services, which currently cross the ECML by a flat junction at Newark, over the ECML; removing this flat junction would improve capacity and reduce operational complexity.
    • capacity improvement works at Finsbury Park, Hitchin, Doncaster, Shaftholme, York, Newcastle and other locations.

    Freight

    The ECML upgrade will yield significant benefits for freight traffic to and from the North East, and includes feasibility studies to handle longer (775m) trains and larger (9’6″ containers and 2.6m wide European intermodal units with an enlarged structure gauge. Plans are also being developed to create additional paths for freight trains on the NE/SW route, the core section of which is Doncaster – Bristol.

    Long Term (Beyond 2010)

    Beyond 2010, the role of the railways will become even more important, and the key network capacity issues will have to be addressed. In particular, this involves:

    • High Speed Line. Additional capacity between London, the North of England and Scotland, for both freight and passenger services; to include consideration of a new line with a high speed capability, and provision of capacity for more north – south rail freight movements;
    • Kings Cross/St Pancras. Integrated development of the main line and Underground stations (and bus and taxi connections) as a ‘superhub;’
    • Multimodal Studies. Development of rail projects identified in the Multi-modal studies;
  • HISTORIC PRESS RELEASE : Strategic Rail Plan – Briefing Note for the South West [January 2002]

    HISTORIC PRESS RELEASE : Strategic Rail Plan – Briefing Note for the South West [January 2002]

    The press release issued by the Strategic Rail Authority on 14 January 2002.

    Briefing Note for the South West

    (The area covered is that of Government Office South West – Gloucestershire, South Gloucestershire, Wiltshire, Swindon, Dorset, Poole, Bristol, South Gloucestershire, North Somerset, Bath & N.E. Somerset, Somerset, Devon, Torbay, Plymouth and Cornwall).

    Objectives

    The Plan sets out how the SRA intends to tackle the rail industry’s problems and priorities in the short, medium and long term to:

    • restore stability in the industry, allowing performance to improve;
    • deliver growth to meet the 10 Year Plan core targets of:
    • 50% increase in passenger kilometres
    • reduction in overcrowding which breaches the SRA’s standards
    • 80% increase in freight tonne-kilometres.
    • build a pipeline of projects at different stages of development against which contractors and suppliers can plan.

    The plan also meets where possible SRA’s other priorities set by Government, including better integration with other transport modes, expansion of capacity and promotion of the use of the railway network.

    The plan also meets where possible the SRA’s other priorities set by Government, including better integration with other transport modes to expansion of capacity to promote the use of the railway network and encourage its use. The priorities have been developed taking into account discussions with the Rail Passengers Committee for Western England, the South West Regional Assembly, the South West of England RDA, Government Office South West, and local authorities within the region. The SRA contributed to the preparation of Regional Planning Guidance, issued in September 2001, and will contribute to the review proposed in 2003. The SRA has also participated in SWARMMS, the London to South West and South Wales Multi Modal Study.

    National schemes with benefits for the South West:

    • Train Protection and Warning Systems
    • A Company Neutral Revenue Support schemes to be introduced in 2002 for intermodal and ‘less than trainload’ markets
    • Freight Facility Grants
    • Freight Small Schemes Fund
    • Incremental Outputs statements for track and signalling and stations
    • Rail Passenger Partnership Fund
    • Training through a National Rail Academy
    • National Rail Performance Fund to improve reliability of services
    • Proposals for a National Test Track to prove new rolling stock, before it is tested on the Railtrack network
    • A programme of improvements for passengers with disabilities to improve station access and special training for staff.

    The principal projects for the South West are set out below.

    Short Term Developments (to 2005)

    • 14 new 5-car Adelante trains with 200 kph capability to be introduced by First Great Western during 2002 for services between London, Bristol and South Wales;
    • New Voyager trains for Virgin’s Cross Country services from Scotland, the North of England and the Midlands via Birmingham, Gloucester, Bristol, Exeter and Plymouth, as well as to and from Bournemouth via Reading. Introduction of Super Voyager tilting trains. Progressive upgrade of 60% of the cross country network to 180 kph or more;
    • Plans have been developed to refurbish part of the HST fleet to provide a quality regular service from Birmingham, Cheltenham and Gloucester via the Stroud Valley to Swindon and London Paddington;
    • A £2.8m freight facilities grant has been made for aggregates from the Mendips to a depot at Colnbrook in West London, now being developed at a total cost of £4.76m;
    • Freight capacity improvements planned between Bristol and Doncaster;
    • Elimination of Mark I slam door coaches from services to Bournemouth and Weymouth by the end of 2004, with safety benefits and better accessibility for passengers with disabilities;
    • Increased capacity at Filton Junction to allow parallel train movements for Cardiff services through the junction;
    • Increased capacity by restoring double track between Worle Junction and Weston-super-Mare, with parallel train movements through the junction at Worle;
    • Provide greater operational flexibility at Bath Spa, Exeter St Davids, Exmouth Junction and between Totnes and Plymouth;
    • New station at Corsham (£2.4m);
    • Reinstating the connection with the Swanage Railway near Wareham, to provide through services between Bournemouth and Swanage (£16.6m)
    • Station and interchange improvements at four stations on the Tamar Valley Line and at Liskeard, Bodmin Parkway and Redruth, funded by the Rail Passenger Partnership scheme;
    • Wessex Trains has 42 stations eligible for upgrading to provide modern facilities. All works are due to be completed by the end of 2004.
    • Bristol area capacity study to look at requirements of light rail between Temple Meads and Filton Junction, as well as other capacity improvements for heavy rail services;

    Medium Term Developments (up to 2005)

    • Infrastructure improvements between Reading and Didcot in conjunction with signalling renewals and development of the key freight route between Southampton and the West Midlands;
    • Development of proposals for upgrading the rest of the Great Western Main Line;
    • Further work to develop proposals for increasing capacity on the Salisbury – Exeter line to provide a more frequent service between Waterloo and Exeter;
    • Gauge clearance feasibility study for larger containers on the GWML to Bristol, and possibly to Exeter/Plymouth;
    • Provide extra signal sections for greater capacity in Cornwall between St Germans and Liskeard, Probus and Burngullow, Bodmin Parkway, Truro – Roskear;
    • Journey time improvements between Exeter and Barnstaple (to permit hourly clockface departures from each end of the line);
    • Capacity improvements for services between Bristol and Portsmouth Harbour, with new turnback facilities at Southampton Central for local trains;
    • Feasibility study on improved gauge clearance work on the GW Main Line to Bristol, and, depending on results, to Exeter/Plymouth .

    Long Term (Beyond 2010)

    Beyond 2010, the role of the railways will become even more important, and the key network capacity issues will have to be addressed. In particular, this involves:

    • Great Western Main Line. Development of plans, linked with track and signalling renewal for the routes from London Paddington to South Wales and the West of England;
    • Rail/air. Further development of airport links, particularly at Heathrow (Airtrack) airport;
    • Crossrail. ‘Regional Express’ cross-city schemes such as the London Crossrail project, being developed jointly with TfL. Similarly, work will continue on the Merton – Hackney route in London.
    • Multimodal Studies. Development and implementation of rail projects identified as required in the Multi-modal studies.
  • HISTORIC PRESS RELEASE : Strategic Rail Plan – Briefing note for the West Midlands [January 2002]

    HISTORIC PRESS RELEASE : Strategic Rail Plan – Briefing note for the West Midlands [January 2002]

    The press release issued by the Strategic Rail Authority on 14 January 2002.

    the area covered is that of the Government Office for West Midlands – West Midlands, Shropshire, Telford and Wrekin, Staffordshire, Stoke-on-Trent, Warwickshire, Worcestershire and Herefordshire)

    Objectives of the Strategic Plan

    The Plan sets out how the SRA intends to tackle the rail industry’s problems and priorities in the short, medium and long term to:

    • restore stability in the industry, allowing performance to improve;
    • deliver growth to meet the 10 Year Plan core targets of:

      – 50% increase in passenger kilometres
      – reduction in overcrowding which breaches the SRA’s s tandards
      – 80% increase in freight tonne-kilometres

    • build a pipeline of projects at different stages of development against which contractors and suppliers can plan.

    The plan also meets where possible SRA’s other priorities set by Government, including better integration with other transport modes, expansion of capacity, and promotion of the use of the railway network.

    The priorities have been developed taking into account dialogue with the Rail Passengers’ Committee for the Midlands, the West Midlands Regional Chamber and Regional Assembly and Advantage West Midlands, Government Office for West Midlands, Centro and local authorities within the region.

    The SRA is contributing to the preparation of the Regional Transport Strategy for the West Midlands.

    The SRA has participated in the following Multi Modal Studies (MMS):

    • West Midlands Area MMS (WMAMMS)
    • West Midlands to North West Conurbation Study (SEMMS)

    National schemes with benefits for the West Midlands

    • Train Protection and Warning Systems
    • A Company Neutral Revenue Support schemes to be introduced in 2002 for intermodal and ‘less than trainload’ markets
    • Freight Facility Grants
    • Freight Small Schemes Fund
    • Incremental Outputs statements for track and signalling and stations
    • Rail Passenger Partnership Fund
    • Training through a National Rail Academy
    • National Rail Performance Fund to improve reliability of services
    • Proposals for a National Test Track to prove new rolling stock, before it is tested on the Railtrack network;
    • A programme of improvements for passengers with disabilities to improve station access and special training for staff.

    PRINCIPAL PROJECTS FOR THE WEST MIDLANDS

    Developments 2001-02

    Service developments

    • Improved Central Trains Birmingham New Street timetable from 2002.

    Rolling stock

    • Birmingham is the focal point for Virgin’s CrossCountry services. 34 four-car CrossCountry Voyager trains will replace all loco-hauled services by May 2002. Progressive introduction of new trains during Autumn/Winter 2001/02, will deliver extra services and greater reliability.
    • A number of existing CrossCountry HST trains are likely to be re-engineered and refitted to operate as high performance five-car trains on new Birmingham-Gloucester-Paddington through services.
    • Testing of first of 44 tilting five-car Super Voyager trains, which will deliver faster journey times.
    • 53 nine-car, 140 mph, tilting VWC Pendolino trains are being constructed by Alstom.
    • Central Trains phase two Class 170 modification programme begun, to improve reliability of the fleet.
    • New air-conditioning units on 72 Central Trains Class 158 vehicles.
    • Modifications to FNW Class 323, 142 and 150 trains to enable staff to carry out enhanced on train customer care and revenue protection duties.

    Performance improvements

    • VWC: £30m investment in improving reliability, quality of passenger experience and maintenance provision
    • VWC: 125 mph operation (present top speed is 110 mph) by May 2003, giving reduced journey times
    • New Central Trains Senior Conductor depot at Birmingham Snow Hill, driver training programme to increase the number of Central Trains drivers.

    Franchise negotiations

    An interim Chiltern franchise agreement took effect from April 2001, to ensure progress whilst a new franchise for up to 20 years is contractualised. The interim agreement commits Chiltern to:

    • 7 extra class 168 vehicles to come into service in summer 2002
    • tougher incentive regime – including penalties for falling below 83% on the SRA’s Public Performance Measure
    • M40 Trains, working with Railtrack and its contractors, to proceed on costings, design and development of schemes which will be committed in the new franchise agreement
    • trial refurbishment of a class 165 to gauge passenger reaction.

    Stations and passenger facilities

    • Station to serve Birmingham ICC being examined (see below)
    • New stations at Rubery and Frankley being examined (see below)
    • Station reconstruction at Rugby.
    • New ticket shop at Stoke-on-Trent station.
    • Redecoration of toilets at twelve Central stations and renovation of toilets at a further four stations.
    • Nuneaton lifts currently being upgraded for passenger use.
    • RPP-funded permanent ticket office at Ludlow.

    Infrastructure improvements

    • Completion of CrossCountry infrastructure upgrade works at bottlenecks.

    RPP proposals
    The following RPP proposals are being assessed:

    RPP proposal Status Output
    Birmingham – Stratford-upon-Avon semi-fast pre-qualification Provision of seven additional return services between Birmingham and Stratford-upon-Avon per day
    Birmingham International Convention Centre pre-qualification New station at ICC Birmingham
    Frankley extension pre-qualification Extend Cross-City services to new stations at Rubery and Frankley

    IOS schemes in the West Midlands

    The SRA is supporting, subject to value for money tests, the following incremental improvements to the network:

    IOS infrastructure scheme Main output Key requirements Expected completion date
    Manchester Airport – Nottingham via Stoke-on-Trent Capacity Regular interval service, running earlier and later 2002
    Longbridge –
    Blake Street
    Capacity Increase the Birmingham Cross-City service to six trains per hour between Blake Street and Longbridge 2002
    Chester –
    Shrewsbury
    journey time Regular interval timetable with reduced journey times. 2002
    Birmingham New Street –
    Bromsgrove – Worcester –
    Hereford
    operational flexibility Provide for Birmingham to Cheltenham via Worcester trains to run via Worcester Foregate Street in both directions 2003 – 04
    Birmingham New Street –
    Bromsgrove – Worcester –
    Hereford
    operational flexibility Space for 4 x 23m car trains to use Birmingham bound platform at Bromsgrove 2003 – 04
    Stourbridge Junction Capacity New 4-car bay platform to provide; a total of 6 trains per hour between Birmingham Snow Hill and Stourbridge Junction; allow a minimum of 4 trains per hour to arrive and turn back 2004 – 05
    Stratford-upon-Avon operational flexibility Ability for passenger trains to arrive and depart from the second platform 2004 – 05
    Kidderminster operational flexibility Ability to turn around a four car set on arrival from Birmingham 2004 – 05
    Droitwich –
    Worcester Foregate Street
    operational flexibility Provide four-minute headways between Droitwich Spa and Worcester 2005 – 06
    Crewe –
    Nottingham
    journey time Reduced journey time 2006-07
    Grand Junction to St Andrew’s Junction operational flexibility Raise the current 15 mph speed limit to 25 mph 2005-06

    Medium Term Developments 2002 – 2005

    Service developments

    • CrossCountry frequencies increased from summer 2003 timetable on core routes, to approximately double the present frequencies, with standard ‘clock face’ timetables and shorter journey times.
    • Frequency improvements on VWC (e.g. 2 trains per hour London to Manchester; three trains per hour London to Birmingham).

    Franchise negotiations

    • The Central Trains franchise is due to expire in 2004. The SRA is looking at the possibility of a two year extension, aimed at achieving an early increase in capacity
    • The present FNW franchise expires in 2004. Services will then move into one of three new franchises:
      • the Northern franchise, with separate business unites to improve local accountability. Expressions of interest have been invited, and tendering will occur early this year.
      • the TranPennine Express franchise, to focus on longer distance fast services and links to Manchester International Airport.
      • the Wales and Borders franchise, which is to be tendered early this year.

    Stations and passenger facilities

    • Birmingham Moor Street station to be expanded.

    Infrastructure improvements

    • WCML Infrastructure upgrade and renewal works to deliver increased capacity, higher line speeds, improved reliability and performance. Remodelling and resignalling on the North Staffordshire route, for higher speeds and reliability.

    West Midlands capacity study

    The SRA, in partnership with Railtrack, Centro, the Government Office for the West Midlands and Birmingham City Council, published the West Midlands Capacity Study in 2001. The capacity study gives an outline programme of two phases of works that could improve network capacity in the West Midlands for passengers and freight.

    The SRA is funding freight-specific works, which are essential for the achievement of the target of 80% growth in freight by 2010. These works will also deliver some limited additional passenger benefits. On the passenger side, in conjunction with regional partners, we shall be developing the strategy further, and examining value for money and affordability issues.

    At present, the SRA does not believe that sufficient funding will be available to support implementation of the overall Phase One works involved before 2010. Subject to clarifying value for money issues, the position could change if increased funding were to be made available.

    The passenger upgrade works proposed by the capacity study would be substantial. If approved, Phase One would take five to seven years to build, and would provide capacity for doubling train seats available, through a series of infrastructure enhancements. On a similar basis, Phase Two would be deliverable in around ten to twelve years, and would further double capacity, through a major upgrade of the Coventry – Wolverhampton corridor.

    West Midlands freight capacity works

    Southampton – West Midlands Felixstowe – Nuneaton. Works to provide increased capacity and increased structure gauge clearances to allow rail to handle 9’6″ containers and European swapbodies more effectively, linking the two largest container ports in Britain with the West Midlands.

    West Midlands network.
    The SRA intends to develop and implement the following:

    • Network capacity to give, in aggregate, a 50% increase in freight paths on the North East
      – South West and North – South corridors across the West Midlands
    • Improved train length and gauge clearance capability on these corridors

    This project would provide capacity across the full West Midlands network to meet projected growth in demand for freight over the next 10 years, and a network of gauge-cleared routes to link the strategic Felixstowe – Nuneaton and Southampton – West Midlands axes. This project develops schemes proposed by the West Midlands Capacity Study, and would have synergies with any future implementation of other schemes from that Study.

    Developments 2001 – 2002

    • Feasibility work in progress on Walsall – Stourbridge reopening (for North East of England/Bescot – South West of England flows)
    • Feasibility work in progress on the Water Oton corridor enhancement (for North – South, North East – South West and Birmingham area flows)
    • Feasibility work on Sutton Park Line upgrade (for North – South, North East – South West and Birmingham area flows)
    • Feasibility work to in progress on Birmingham – Wolverhampton signalling headways (for North – South and Birmingham area flows)

    Developments 2002 – 2005

    Outputs Expected completion date
    Water Orton corridor remodelling and signalling. 2004 – 05
    Walsall – Stourbridge reopening. 2004 – 05
    Sutton Park line upgrade. 2005

    Developments 2005 – 2010

    Outputs Expected completion date
    Birmingham – Wolverhampton signalling headways. 2006
    Other Schemes Developments 2002 – 2005 Developments 2005 – 2010
    Midland Main Line: incremental capacity
    • Bolt-on enhancements during the Trent Power Signal Box renewal project
    • Freight loops at Desborough
    • Provision of minimum two paths per hour for freight on all route sections
    West Coast: capacity for freight growth North of Crewe
    • Enhancement to enable freight levels to grow when passenger service levels are increased under WCRM
    • Enhancement to created through paths North and South of Crewe
    North East – South West axis
    • Additional feasibility work to see what could be delivered before 2005
    • Provisions of a minimum two paths per hour for freight between Bristol and Doncaster

    Long Term (Beyond 2010)

    Beyond 2010, the role of the railways will become even more important, and the key network capacity issues will have to be addressed. In particular, this involves:

    • High Speed Line. Additional capacity between London, the North of England and Scotland for both freight and passenger services; to include consideration of a new line with a high speed capability, and provision of capacity for more north – south rail freight movements;
    • West Midlands/Manchester Capacity. Relief of congestion with new infrastructure in regional centres such as Birmingham and Manchester;
    • Multimodal Studies. Development and of rail projects identified in the Multi-modal studies;
  • HISTORIC PRESS RELEASE : Strategic Rail Plan – Briefing note for Yorkshire and the Humber [January 2002]

    HISTORIC PRESS RELEASE : Strategic Rail Plan – Briefing note for Yorkshire and the Humber [January 2002]

    The press release issued by the Strategic Rail Authority on 14 January 2002.

    (the area covered is that of Government Office for Yorkshire and the Humber – North Yorkshire, East Riding of Yorkshire, City of York, West Yorkshire, South Yorkshire, North East Lincolnshire and North Lincolnshire)

    Objectives of the Strategic Plan

    The Plan sets out how the SRA intends to tackle the rail industry’s problems and priorities in the short, medium and long term to:

    • restore stability in the industry, allowing performance to improve;
    • deliver growth to meet the 10 Year Plan core targets of:

      – 50% increase in passenger kilometres
      – reduction in overcrowding which breaches the SRA’s standards
      – 80% increase in freight tonne-kilometres

    • build a pipeline of projects at different stages of development against which contractors and suppliers can plan.

    The priorities have been developed taking into account dialogue with the Rail Passengers’ Committee for North Eastern England, the Yorkshire and Humber Regional Assembly and Yorkshire Forward (the RDA), Government Office for Yorkshire and the Humber and local authorities within the region.

    The SRA contributed to the preparation of Regional Planning Guidance for Yorkshire and the Humber, issued in October 2001.

    The SRA has participated in the following Multi Modal Studies (MMS):

    • South and West Yorkshire Multi Modal Study (SWYMMS)
    • Hull East West Corridor (HUMMS).

    National schemes with benefits for Yorkshire and the Humber

    • Train Protection and Warning Systems
    • A Company Neutral Revenue Support schemes to be introduced in 2002 for intermodal and ‘less than trainload’ markets
    • Freight Facility Grants
    • Freight Small Schemes Fund
    • Incremental Outputs statements for track and signalling and stations
    • Rail Passenger Partnership Fund
    • Training through a National Rail Academy
    • National Rail Performance Fund to improve reliability of services
    • Proposals for a National Test Track to prove new rolling stock, before it is introduced on the Railtrack network.
    • A programme of improvements for passengers with disabilities to improve station access and special training for staff.

    PRINCIPAL PROJECTS FOR YORKSHIRE AND THE HUMBER

    Developments 2001-2002

    Service developments

    Rolling stock

    • 34 four-car CrossCountry Voyager trains to replace all loco-hauled services by May 2002. Progressive introduction of new trains during Autumn/Winter 2001/02, delivering extra services and greater reliability. Testing of first of 44 tilting five-car Super Voyager trains, which will deliver faster journey times.

    Performance improvements

    • Draft enforcement order made against Arriva Trains Northern, and further incentives put in place, to restore and improve train services.

    Stations and passenger facilities

    • The SRA has contributed development funding for a programme of improvements at Sheffield station, which are the subject of a Rail Passenger Partnership bid.
    • · RPP-funded redevelopment of Thornaby station (including new staffed station building).

    Infrastructure improvements

    • ‘Leeds First’ project, phase 1a of the ECML upgrade, will be completed, comprising resignalling, additional track and platform capacity, a new station roof, customer information systems, and a new footbridge with lifts and escalators.
    • CrossCountry: completion of infrastructure upgrade works at bottlenecks.
    • SRA is procuring design feasibility studies for further elements of the East Coast Main Line upgrade.

    Rail Passenger Partnership proposals

    The following RPP proposals are currently being assessed:

    RPP proposal Status Output
    Sheffield station Pre-qualified Redevelopment and refurbishment of Grade II listed station & environs, better integration with Supertram, local bus network & city centre
    North East Yorkshire Rail Scheme Revised bid expected Two new railway stations and a regular service between Strensall, Haxby and York

    IOS infrastructure

    The SRA is supporting, subject to value for money tests, the following incremental improvements to the network:

    IOS infrastructure scheme Main output Key requirement Expected completion date
    Nottingham – Sheffield Capacity 2 trains per hour at regular intervals 2003-04
    Sheffield to York operational flexibility upgrade the Monkhill Goods line to passenger status, allowing new through services 2005-06

    Short Term Developments 2002-2005

    Service developments

    • CrossCountry: frequencies increased from summer 2003 timetable on core routes, to approximately double the present frequencies, with standard ‘clock face’ timetables and shorter journey times.
    • 3 additional Midland Main Line services in each direction between Sheffield and London from May 2004.
    • MML: extension of London – Sheffield services to provide hourly trains to and from Leeds between 0700 and 1900 from May 2004.

    Rolling stock

    • 127 new 125 mph diesel vehicles to replace the present 100 mph MML Turbostar trains by 2005, giving a one third increase in total train capacity.
    • Interior refurbishment of MML HSTs.
    • Provision of MML depot in Yorkshire.
    • Metrotrain RPP bid for eight additional Class 333 trailer cars (on an existing Class 333 fleet of 48 vehicles) and platform extensions on the Leeds – Doncaster line has been approved.
    • Funding for another eight new class 33 trailer cars approved, and for leasing an additional ten vehicles, the former Airedale and Wharefdale services, the latter for routes in West and South Yorkshire.

    Performance improvements

    • Profit sharing between MML and the SRA will begin from 2004; all payments due to the SRA will be reinvested in commensurate passenger benefits.

    Franchise negotiations

    • TransPennine Express: in September 2001, the SRA was requested by Secretary of State to proceed towards the final stage of the letting of this franchise. Formal consultations with the 5 PTEs, which have the statutory right to specify services in their respective regions, were completed last year. 3 shortlisted counterparties will shortly be invited to submit revised proposals, taking into consideration any additional requirements emerging from the consultation process. It is intended that the new franchise will be awarded later this year, to commence early next year. The new franchise will look at opportunities for new rolling stock and depot facilities; more frequent express services on key routes; and addition of new destinations to the TPE network, as well as continuing design development work on Calder Valley upgrade.
    • SRA is negotiating a 2 year franchise extension with GNER to 2005 and details will be announced shortly. Essential requirements include:
      • additional incentives for improved operational performance and customer satisfaction
      • interior refurbishment of all existing IC225 and HST trains
      • a programme of HST reliability modifications
      • station improvements.

    Stations and passenger facilities

    • £22m of enhancements to MML stations, including improvements to stations car parks, passenger information systems, ticketing information, passenger information regarding transport interchange facilities, and cycle storage facilities.
    • Sheffield station – SRA has contributed funding for development work on major improvements to Sheffield station. The Government’s 2002-03 Local Transport Settlement includes £7.65m for improved pedestrian access to, and facilities at, the station.

    Infrastructure improvements

    ECML Upgrade: SRA’s intention is to lead a Joint Venture company that will deliver an upgrade of passenger and freight capacity on the ECML. Improvements could include:

    • Longer trains and platforms
    • Remodelling of Peterborough station
    • Development of alternative freight lines to provide increased and segregated capacity between:
      • Peterborough and Doncaster via Lincoln
      • Doncaster and York
      • Northallerton and Ferryhill via Teeside
      • Newcastle and Edinburgh, through provision of freight loops
    • New bridge to take East-West services, which currently cross the ECML by a flat junction at Newark, over the ECML; removing this flat junction would improve capacity and reduce operational complexity.
    • Capacity improvement works at Finsbury Park, Hitchin, Doncaster, Shaftholme, York, Newcastle and other locations.
    • ATN will gain spin-off benefits from the MML and ECML upgrades

    Freight

    The South Humberside Main Line currently handles approximately 20% of all UK rail freight tonnage. Improved capacity and speeds will consequently benefit a wide range of freight customers. Improvements on the capacity-constrained Hope Valley line will provide more freight paths, faster transits and greater reliability, which also provide benefits for passenger operators. Improvements at Doncaster will also take place to accommodate longer freight trains.

    The SRA intends to develop and implement the following:

    • Increase in the availability of freight paths in the order of 30% to/from ports at Immingham, Grimsby, and Killingholme
    • Increase in speeds for freight trains between Doncaster and Immingham
    • Reopening of the Wrawby Junction – Brigg – Gainsborough route to add capacity to and from the South Humberside area
    • Incremental improvements to capacity, speed and route availability for freight trains on the Hope Valley line between Sheffield and Manchester
    • Gauge clearance to W10 or W12 on the North TransPennine Route between Leeds and Manchester, including connections to ports and terminals

    Freight Developments 2002 – 2005

    Outputs Expected completion date
    Wrawby Junction – Gainsborough reopening. 2002
    Hope Valley incremental speed and route availability improvements. 2002 – 04
    South Humberside Main Line, speed improvements, minor signalling works. 2002 – 04

    In the period 2005 – 2010, additional capacity for freight trains is planned on the route between Doncaster band Bristol.

    Long Term (Beyond 2010)

    Beyond 2010, the role of the railways will become even more important, and the key network capacity issues will have to be addressed. In particular, this involves:

    • High Speed Line. Additional capacity between London, the North of England and Scotland for both freight and passenger services; to include consideration of a new line with a high speed capability, and provision of capacity for more north – south rail freight movements;
    • Kings Cross/St Pancras. Integrated development of the main line and Underground stations (and bus and taxi connections) as a ‘superhub;’
    • Multimodal Studies. Development of rail projects identified in the Multi-modal studies;
  • HISTORIC PRESS RELEASE : Strategic Rail Plan – Briefing Note for the South East [January 2002]

    HISTORIC PRESS RELEASE : Strategic Rail Plan – Briefing Note for the South East [January 2002]

    The press release issued by the Strategic Rail Authority on 14 January 2002.

    (The area covered is that of the Government Office for London and the Government Office for the South East – Greater London, Berkshire, Buckinghamshire, Hampshire, Isle of Wight, Kent, Oxfordshire, Surrey, East Sussex, West Sussex).

    Objectives of the Strategic Plan

    The Plan sets out how the SRA intends to tackle the rail industry’s problems and priorities in the short, medium and long term to:

    • restore stability in the industry, allowing performance to improve;
    • deliver growth to meet the 10 Year Plan core targets of :

      – 50% increase in passenger kilometres
      – reduction in overcrowding which breaches the SRA’s standards
      – 80% increase in freight tonne-kilometres

    • build a pipeline of projects at different stages of development against which contractors and suppliers can plan.

    The plan also meets where possible SRA’s other priorities set by Government, including better integration with other transport modes, expansion of capacity and promotion of the use of the railway network.

    The priorities have been developed taking into account dialogue with the Rail Passengers’ Committees for Southern and Western England, the London Transport Users Committee, Transport for London, the Government Offices for London, the Government Office for the South East and local authorities within the region.

    The SRA is contributing to the preparation of the Regional Transport Strategy for the South East and maintains dialogue on the Mayor’s strategy for Greater London.

    The SRA is currently taking part in the DTLR-sponsored Multi-Modal Study (MMS) process, and is represented on all the MMS Steering Groups. Some twenty studies are underway or have been completed in England.
    As requested by the Secretary of State, the SRA is currently undertaking further work on the rail issues associated with the Access to Hastings Study, which was the first study Ministers considered.

    National schemes with benefits for the South East:

    • Train Protection and Warning System
    • A Company Neutral Revenue Support schemes to be introduced in 2002 for intermodal and ‘less than trainload’ markets
    • Freight Facility Grants
    • Freight Small Schemes Fund
    • Incremental Outputs statements for track and signalling and stations
    • Rail Passenger Partnership Fund
    • Training through a National Rail Academy
    • National Rail Performance Fund to improve reliability of services
    • Proposals for a National Test Track to prove new rolling stock, before it is tested on the Railtrack network
    • A programme of improvements for passengers with disabilities to improve station access and special training for staff

    Schemes of Particular Relevance for the South East

    Priorities-Short Term

    • Some 1,700 new coaches to be introduced on the South Central, Connex South Eastern and South West Trains franchises by 2004
    • Completion of the Train Protection Warning System (TPWS)
    • East London Line. The extension of the East London Line to North and South will provide a new cross-London link, help regeneration and contribute to the further development of Docklands. The SRA has committed £39m for project development. Completion of the Channel Tunnel Rail Link. Section 1 is scheduled for completion by 2003 and Section 2 to St Pancras by 2007

    National projects with implications for London and the South East also include:

    • The establishment of a Rail Performance Fund in order to provide added resilience to the network
    • An ‘Accessibility for All’ programme which includes additional funding to ensure that TOCs, where necessary, are able to implement the requirements of the Disability Discrimination Act
    • Simplification of the franchise structure by bringing services at key London terminals under single control wherever possible thereby reducing operational conflicts at congested parts of the network

    Priorities-MediumTerm

    • Replacement of the Chiltern, South Central and South West Trains franchises which will deliver new rolling stock, increased capacity, greater reliability and better integration with other transport modes
    • Progress on the Thameslink 2000 project, providing Metro style frequencies through the centre of London
    • Platform extensions to accommodate longer trains on the Connex South Eastern, Great Northern and First Great Eastern franchises
    • Capacity improvements on the London -West Anglia route, incuding Stansted Airport

    In parts of London and South East England, introduction of new trains for improved services is contingent on upgrades to the power supply. Work is underway to scope the costs and feasibility of doing this within the timescale required.
    Passenger Service Requirements (PSRs), set out the minimum service operators must provide. They are being reviewed to establish whether changes could deliver a more robust timetable and extra capacity. The SRA is seeking to identify priorities for early action.

    The principal projects for the South East are set out below.

    Channel Tunnel Rail Link

    The Channel Tunnel Rail Link (CTRL) is a completely new high speed rail link from the Channel Tunnel to London St. Pancras. It will provide high speed running for Eurostar services and for fast new domestic services linking major stations in Kent with St.Pancras. It will contribute to regeneration in the Thames Gateway area, east London, around St.Pancras and in several areas of Kent.

    Developments (2002-2005)

    • CTRL Section One is two thirds complete, and is expected to open in 2003. It runs from the Channel Tunnel to the Thames Estuary, joining the Railtrack network at Fawkham Junction; to allow Eurostar trains to serve Waterloo; Eurostar journey times will be significantly reduced and release more capacity on the route via Tonbridge

    Developments (2005-2010)

    • CTRL Section Two extends the new rail link from Ebbsfleet under the Thames to St Pancras. Work commenced in 2001, and the route is expected to be open early in 2007. Works include:
    • a new international station at Stratford, providing fast links to Paris and Brussels from Docklands
    • St Pancras remodelling, to accommodate Eurostar trains with an extension to the original train shed, and new platforms both for services using the Midland Main Line and domestic services from the CTRL
    • Construction of a new sub-surface station box at St Pancras and a tunnel link to the Great Northern route. The Thameslink 2000 project provides for fitting out this low level station and joining it to the Great Northern route at Belle Isle junction, North of Kings Cross. This will allow Great Northern services to be integrated into the Thameslink network
    • Fast domestic services will serve Ashford. Ebbsfleet, Stratford and St Pancras International
    • Fast domestic services are also expected to serve North West Kent and the Medway Towns, Ramsgate. Canterbury, Dover and Folkestone
    • Works to improve interchange at St Pancras- Kings Cross
    • Completion of CTRL Section Two will release land in the Kings Cross area for redevelopment
    • Preparations for the franchising process for the fast domestic services commenced last year ; a franchise proposal will be published by the SRA later this year
    • New high speed trains will need to be procured for domestic services
    • With Sections One and Two completed, CTRL will have capacity for up to eight Eurostar services per hour in each direction and up to eight domestic services in each direction in the peaks. The railway also has the potential to handle freight trains adapted to operate at high speeds
    • Journey times to Paris and Brussels will be reduced by over half an hour compared with today. There will be major domestic journey time improvements too; an example is a new journey time from Ashford to London of 37, against the current 75 minutes
    • Some capacity on the South East London suburban network will be released

    Chiltern Railways

    Developments 2001-2001 A Deed of Amendment to the existing franchise agreement took effect from April 2001. This ensures progress while the new franchise, for up to twenty years, is contractualised. The interim agreement commits Chiltern to:

    • Seven extra Class 168 vehicles to come into service in Summer 2002
    • Tougher incentive regimes- including penalties for falling below 83% on the SRA’s Public Performance Measure
    • 580 extra parking spaces, at seven stations, by March 2002
    • M40 Trains ( the parent company of Chiltern railways), working with Railtrack and its contractors, to proceed on the costing, design and development of schemes which will be committed in the new Franchise Agreement (see below)
    • Trial refurbishment of a Class 165 train to gauge passenger reaction

    Developments 2002-2005 The following major commitments will be included in the new Franchise Agreement, which is currently being finalised:

    • Restoration of double track and an increase in line speed between Bicester North and Aynho Junction by August 2002. This will facilitate increased peak services to Banbury, Bicester North and Haddenham and Thames Parkway and provide a diversionary route for passengers during engineering work on the Southern end of the West Coast Main Line
    • Two extra platforms at London Marylebone and a new depot in the London area
    • An increase in the peak frequency to High Wycombe
    • Platform length extensions to accommodate eight –car trains at twelve stations ,for completion between May 2002 and May 2003
    • Fifteen new vehicles, for delivery in phases between Winter 2002 and Winter 2004, and a commitment for the future to order sufficient rolling stock to meet demand up to agreed levels
    • All Class 165 rolling stock to be refurbished to an agreed standard for completion in 2004,or replaced by 2006
    • Improved passenger information, security and accessibility at Chiltern stations, and some other stations served by Chiltern
    • Fifteen out of sixteen of all trains, all day, to arrive at their destinations within SRA punctuality standards from the end of 2003
    • Project management of the trial of ERTMS ( the train control system) on the route

    Developments (2005-2010) The duration of the Chiltern franchise will be reviewed in 2005, in the light of
    achievement on the commitments above, and progress made on developing further schemes, including:

    • Further infrastructure enhancement work, including restoring four tracks between West Ruislip and Northolt Junction, and through Beaconsfield
    • Upgrade of the route between London and Aylesbury via Amersham, to improve journey times and service frequencies
    • West Hampstead interchange station
    • New services Aylesbury/Oxford/Bletchley/Milton Keynes ( a route closed to passenger services in the 1960’s)
    • Development of an extension North of Aylesbury, to a new M1/M6 Parkway station
    • In the event that capacity is available, the operation of half-hourly local all-stations services in Greater London

    Connex South Eastern
    Developments 2001-2002

    • Introduction of 210 vehicles of new Class 375 rolling stock by Summer 2002
    • Investments of £40.5m in rolling stock reliability improvement for Class 465,466 and 508 trains

    Developments 2002-2005

    • Connex South Eastern ( CSE) are required to replace all remaining Mark 1 rolling stock by the end of 2004 at the latest

    CSE are preparing a proposal for an extension, which is expected to contain the following features:

    • Refurbishment of all Class 465, 466 Networker vehicles and redeployment of some of the fleet on Kent Weald services.
    • 180 purpose built Metro vehicles for lines from Dartford and Hayes to London Bridge, Charing Cross and Cannon Street, specially designed to deal with high numbers of boarding and alighting passengers
    • additional vehicles to accommodate growth and reduce overcrowding
    • extending platforms on the Gillingham and Dartford via Greenwich routes to accommodate twelve car trains ( platforms on the Dartford via Bexleyheath and Sidcup routes are to be extended to accommodate twelve-car trains under the Thameslink 2000 project), to increase capacity and reduce overcrowding

    IOS stations
    CSE has 145 stations eligible for upgraded facilities under the IOS scheme. The works are due to be completed by the end of 2004.

    IOS infrastructure
    The SRA is supporting, subject to value for money tests, the following incremental improvement to the network:

    IOS infrastructure Main output Key requirement Expected completion date
    Tunbridge Wells Operational Flexibility Twelve-car trains able to turn back at both platforms 2004-2005

    RPP Proposal
    The following RPP proposal is currently being assessed for possible funding

    RPP Proposal Status Output
    Camberwell Station pre-qualified New station (CSE and Thameslink). New Herne Hill-Blackfriars shuttle to provide additional capacity.

    East London Line

    The extension of the East London Line to North and South will provide a new cross-London link. It will help regeneration and contribute to the further development of Docklands. The East London Line is currently operated by London Underground, from Shoreditch to New Cross and New Cross Gate. The SRA, Transport for London and the Mayor for London have agreed that the line will be developed to the standards of the national rail network.

    The line is to be extended North (partly over old railway infrastructure) to a new junction at Dalston, allowing through services to Highbury, Islington and beyond, and South to destinations including Wimbledon , Crystal Palace and West Croydon. Transport for London has plans to integrate bus and Underground services with the expanded East London Line, and new interchanges will be provided at Dalston Junctionand Shoreditch (Bishopsgate), as well as new stations at Hoxton and Haggerston.

    The extension will be built under a Private Finance Initiative concession, under which the private sector will design, build, finance and maintain the project. The concession will be awarded by the SRA. Powers to construct the extension were obtained in 1997 for the Northern extension, and in October 2001 for the Southern section.
    Work on the Northern extension has begun. The target for the opening of the entire extension is 2006.

    Developments (2001-2002)

    • The SRA has committed £39m for project development, sufficient to purchase and to allow a start to engineering works on the Northern section; works have begun.
    • LUL have begun works in the Dalston, Bishopsgate Goods Yard and Allen Gardens area.

    Developments (2002-2005)

    • Major works on the Northern section are scheduled to be commenced by LUL this Autumn on bridges at Kingsland, Dalston and Shoreditch
    • The SRA will let the concession for the extension later this year, and control of works will then pass to the concessionaire
    • New stations will be built in Hoxton, Haggerston and Dalston Junction, and on the site of the old Bishopsgate Goods Yard
    • Works on the Southern extension will be progressed in parallel once the concession has been awarded
    • New trains will be procured

    Developments (2005-2010)

    • North-South services on the East London Line are intended to be a stepping stone to the creation, in the longer term, of an Orbirail franchise, linking with services on the North London Line, and possibly the West London Line, to provide an orbital alternative to journeys across the central areas of London.

    First Great Eastern*

    The present franchise expires in 2004, and will be replaced by a new Greater Anglia franchise, comprising, this area’s services, West Anglia and Anglia services; the key benefits in the Great Eastern area will include:

    • More effective use of capacity into Liverpool Street station, to provide a better service and reduce overcrowding
    • Possible capacity improvement on the Great Eastern Main Line route

    IOS stations
    First Great Eastern has 40 stations eligible for upgrading facilities under the IOS scheme. The works are due to be completed by the end of 2004.

    RPP Proposal
    The following RPP proposals is currently being assessed for possible funding:

    RPP proposal Status Output
    Stratford station Pre-qualified Extended platform and revised signalling to allow more peak services to stop.

    * See Eastern England briefing for details of developments in Essex and Suffolk.

    Gatwick Express

    Developments 2001-2002

    • Additional luggage facilities to be added to the new fleet of Class 460 Juniper trains
    • New portable ticket issuing equipment

    Development 2002-2005

    • Gatwick Express is seeking to reduce journey times between London and Gatwick to 28 minutes, and to start trains on the hour, half and quarters, from both ends of the route; these changes will take some time to be incorporated in the timetable
    • Feasibility studies are currently being undertaken on Victoria check-in facilities, to explore the possibilities of expanding/improving the facilities available to passengers

    Island Line
    Developments 2001-2002

    • Two year franchise extension to September 2003 agreed with Stagecoach in March 2001
    • The franchise extension commenced in October 2001 and provides an improved Passenger’s Charter ( including added customer benefits); it gives the franchisee additional incentives to maintain good performance, by providing for refunds for serious delays or cancellations and sets a stringent penalty threshold for season ticket refunds
    • Additional services from Ryde Pier Head to Shanklin on High Summer Saturdays, to provide three trains per hour, sponsored by the ferry operator Wightlink.
    • Installation of “Train Stop” system, which applies the brakes on any train passing a signal at danger
    • A report commissioned by the SRA investigated future options for rail service provisions on the Island; consultation on the report has been completed and the SRA is now developing its strategy in the light of the results of the consultation

    Developments 2002-2005

    • The SRA will start discussions on the replacement of the current franchise early this year
    • Consideration is being given to work to remove a speed restriction at Rowborough

    Silverlink

    Developments 2001-2002

    • Secure station accreditation being sought for eight stations
    • Real time train information fed to screens at North London Line stations

    Developments 2002-2005

    • Silverlink Metro to open new telephone lines providing route and timetable information
    • The SRA, Silverlink and Angel Trains are in final negotiations to acquire three three-car Class 508 trains to relieve overcrowding: the SRA has approved these trains for introduction in 2002 subject to final negotiation; this will enable Silverlink to deliver additional peak services on the North London Line between Stratford and Camden Road, to alleviate severe overcrowding
    • Silverlink are making proposals for a two-year extension. The aim would be additional capacity, particularly on the North London Line

    There appear to be advantages in terms of making best use of available network capacity, in combining the Virgin West Coast and Silverlink franchises or services operating into Euston. The SRA is consulting with stakeholders on the general principle of single management of services into each of the London terminals, and will announce its conclusion shortly. Combination could take place at the expiration for the Silverlink franchise, in 2004, or possibly before, if suitable terms could be agreed. In addition, an option for the Metro services would be to transfer them to form the core of the proposed Orbirail franchise with in due course, services on the extended East London Line.

    IOS stations

    Silverlink had 53 stations eligible for upgraded facilities under the IOS scheme. The works are due to be completed by the end of 2004

    IOS infrastructure

    The SRA is supporting, subject to value for money tests, the following incremental improvements to the network:

    IOS infrastructure Main output Key requirement Expected completion date
    Barking Operational Flexibility Ability to run two trains from Gospel Oak into one platform 2005-06
    Willesden Junction
    (High Level)
    Operational Flexibility Ability to turn back trains in a central siding 2004-05

    RPP proposals
    The following RPP proposals are currently being assessed:

    RPP proposal Status Output
    Willesden to Clapham approved Summer Sunday service, to start Summer 2002
    West London line under appraisal Improved services; new stations at Shepherd’s Bush and Chelsea Harbour

    South Central

    Developments 2001-2002 Govia, which operates services under the South Central name, was selected as the preferred counterparty for the new South Central franchise; the existing franchise has been transferred from Connex to Govia to allow Govia to begin its development programme as soon as possible.

    Over the coming months SRA will be working with Govia to contractualise the heads of terms for the new Franchise Agreement.

    Developments 2002-2005 The heads of terms between Govia and the SRA announced on 24 October 2000 included the following commitments from Govia. Signature of the new Franchise Agreement is currently anticipated to be in late 2002.

    • 400 new Electrostar vehicles to be introduced into service during 2002-2003, operating the majority of off-peak and some peak services during 2003
    • a further 300 Electrostar vehicles ( or equivalent) to allow all Sussex Coastway services to be operated by Electrostars ( or equivalent) from December 2004
    • Mark 1 stock released by introduction of Electrostar vehicles to be used initially for peak strengthening, with full withdrawal of Mark 1 stock by the statutory date of 31 December 2004
    • Electrification of lines from Hurst Green to Uckfield, and Ore to Ashford, allowing for electric operation between Ashford International – South Coast and Uckfield – London
    • Station improvements
    • Increased depot capacity
    • Platform lengthening
    • “Stakeholder Board” to be introduced to give passengers a voice in the development of the franchise
    • Passenger’s charter improvements include compensation for delays and missed connections, more customer focused compensation arrangements and a commitment to improve information and customer service, from commencement of the new Franchise Agreement
    • Commitment to nine out of ten trains arriving within SRA punctuality standards

    South London

    • Enhancement of the South London Metro suburban services, including all-day services with generally higher frequencies from early morning to late evening, earlier first trains, later last trains, and longer trains on some routes, giving four trains per hour on eight out of ten Metro routes
    • Refurbishment of all power door rolling stock to improve both passenger environment and reliability, including all Class 455 and 456 trains

    Brighton Main Line

    • Enhancements at Gatwick Airport station for performance and capacity gains
    • Improved frequency and journey to Sussex Coast, and infrastructure work including a new flyover at Windmill Bridge Junction on the Brighton Main Line, a capacity bottleneck

    Sussex Coastway

    • Infrastructure facilities to allow trains to overtake slower stopping services on the Coastway route

    Arun Valley

    • Upgrade of Arun Valley line, improving line speed and capacity, and providing diversionary and relief route for Brighton Main Line via a new East facing chord with the Coastway route
    • Upgrade of Sutton route, including the development of track and station facilities at Epsom station

    IOS infrastructure
    The SRA is supporting, subject to value of money tests, the following incremental improvements to the network:

    IOS infrastructure scheme Main output Key requirement Date
    Clapham Junction to Mitre Bridge Operational flexibility Reduce headway to three minutes by raising line speed 2004-5
    Havant-Brighton Flexibility Provide facilities at Worthing to permit fast services to overtake slow services.

     

    • As part of a package of investigations, Railtrack has at the SRA’s request, employed consultants to survey the electric traction power supply on part of the South Central area
    • The heads of terms between Govia and the SRA also included a commitment from Govia to introduce additional trains into service each year throughout the duration of the franchise to meet expected demand; up to a total of 1000 new vehicles could enter service between 2001 and 2010

    South West Trains
    Developments 2001-2002

    • “Full Crew” working, where Guard, Driver and train stay together for working shift, allowing faster service recovery in times of disruption
    • continued introduction of New Class 458 Jupiter trains
    • sanding equipment for better running in poor conditions, already fitted to all Class 159 trains and to be fitted to all Class 455 by the end of 2001

    The SRA has agreed heads of terms with Stagecoach to replace the South West Trains franchise with a new twenty year franchise. The two parties making progress towards signing of the replacement Franchise Agreement

    Developments 2002-2005

    • RPP-funded scheme to modernise Brentford station, work due to commence this year: enhanced services already commenced

    Commitments to the following improvements are included in the heads of terms agreed between the SRA and South West Trains:

    • 785 new Siemens Desiro vehicles have been ordered to replace existing Mark 1 stock and provide additional capacity to relieve overcrowding
    • additional services on weekday evenings to Southampton, Portsmouth, Hampton Court, Dorking, Kingston, Shepperton, Windsor and Guildford via Cobham
    • additional Sunday services to Portsmouth, Reading, Windsor, Hampton Court, Chessington and Guildford via Cobham
    • longer platforms at Waterloo and 60 other stations to accommodate trains up to ten cars, in place of the present eight cars. This will give a further increase in peak capacity over most of the suburban system
    • a recast of the timetable from Reading and Windsor to Waterloo, and the Main Line timetable. This will provide overall 16% increase in peak capacity to Waterloo, and a frequency of at least four trains per hour at suburban stations on both the Richmond and Hounslow lines
    • introduction of a four trains per hour frequency between Shepperton and Kingston
    • generally higher frequencies from early morning to late evening

    IOS infrastructure

    The SRA is supporting, subject value for money tests, the following incremental improvements to the network:

    IOS infrastructure scheme Main output Key requirement Date
    Farnborough Operational flexibility 50mph crossovers 2005-06

    RPP proposals
    The following RPP proposals are currently being processed:

    RPP proposal Status Output
    Chandler’s Ford Station pre-qualified New station, with car and cycle parking.

    Developments 2005-2010
    Further proposals in the Heads of Terms include:

    • redevelopment of Clapham Junction, including overbridge or upper concourse with lift or escalator access to platform level, passenger lounges and improved shelter on platforms
    • passenger circulation improvements at Waterloo
    • upgrading of Wimbledon and Vauxhall stations to improve interchange with the London Underground
    • proposals for improving the reliability of infrastructure to give better punctuality of services
    • improved facilities, including CCTV linked to British Transport Police control, at all stations
    • toilets and improved waiting areas at all staffed stations
    • all platforms accessible to people with disabilities by 2014
    • introduction of a four trains per hour frequency between Hampton Court and Surbiton

    Thames Trains

    Developments 2001-2002

    • refurbishment of Class 166 trains ( over one third of total fleet)
    • £2m to be spent on station improvements in 2001-02
    • TrainBus campaign of integrated rail- link buses, integrated tickets in all conurbations served, and other areas, and special connections for towns not served by rail

    Developments 2002-2010

    • Thames Trains to project manage the trial of the ERTMS train control system on the route.

    The Thames Trains franchise expires in 2004. There is a possibility of a two-year extension, with passenger benefits, which could include increased capacity. There appear to be advantages, in terms of making the best use of available network capacity, in combining the Thames Trains franchise with the Great Western Franchise; an opportunity could arise at the replacement of the First Great Western franchise in 2006. The SRA is consulting with stakeholders on the general principle of uniting management of services into each of the London terminals under single operators, and will announce its policy shortly.

    Key issues for any new franchisee for the Thames Trains area will include:

    • Additional rolling stock, to provide extra capacity.
    • Journey time improvements
    • Improved integration with Heathrow Airport
    • Car parking capacity

    IOS stations – Thames has 36 stations eligible for upgraded facilities under the IOS scheme. The works are due to be completed by the end of 2004.
    IOS infrastructure

    IOS infrastructure scheme Main output Key requirement Date
    Newbury Operational flexibility Provide for passenger trains to terminate in the down platform and turn back towards Reading 2004-5

    Thameslink

    Developments 2001-2002

    • Timetable improvements from Bedford and Luton to London from Summer 2001. Faster ‘clock-face’ services between London and Gatwick, and four trains per hour between London and Gatwick stopping only at East Croydon.
    • Secure station accreditation achieved at Tooting, South Merton, St Helier, Sutton Common, Haydons Road, Wimbledon Chase, Morden South, City Thameslink, Leagrave and West Sutton. Also being pursued for Hendon, West Hampstead and Cricklewood stations.
    • TPWS fitted to all Thameslink 319 units.

    Developments 2002-2010

    • Proposals to increase level of morning peak service in the Northern part of the franchise being considered for Winter 2002
    • Review of timetable provision, to take advantage of synergies with South Central services
    • Development of proposals for improved maintenance and stabling facilities
    • The “Capability” project will be rolled out, following a trial at St. Albans. This project is designed to enable staff to react more readily, and with authority, to customers’ needs
    • Acceleration of the renewal of signalling in the London Bridge area, which will allow increased flexibility in engineering possessions during implementation of the Thameslink 2000 project
    • The Thameslink franchise expires in 2004. Eight companies pre-qualified, in 2000, to bid for an enlarged franchise, including Great Northern services and certain services south of the Thames. The conclusions of the SRA-Railtrack procurement review for the Thameslink 2000 project announced in April 2001 will inform the franchise proposition offered. A further announcement will be made later this year. There is also a possibility of a two-year extension of the franchise to secure additional capacity. The extension could include the transfer of Great Northern services to Thameslink

    Thameslink 2000
    The Thameslink 2000 scheme is a major project subject to a contract between Railtrack and the SRA. It is dependent upon on the conclusions of a Transport and Works Act inquiry, the hearings of which ended in May 2001. If approved by the Secretary of State, the SRA expects to start in 2003, and to be completed in 2008. Principal outputs would be as follows:

    • Capacity to enable 24 trains per hour in each direction between Kings Cross and Blackfriars in peak periods, 18 of which would serve London Bridge
    • Platform extensions to accommodate 12-car trains on most of the routes intended to be used by Thameslink 2000 services, considerably increasing capacity, and reducing overcrowding
    • Linking of the Great Northern route into the central Thameslink section, increasing through journey and interchange opportunities, and thus relieving not only the existing Thameslink catchment areas and services on the Great Northern, but also major London interchanges, by offering more through destinations to and from South of London

    IOS station – Thameslink has 21 stations – works to be completed by end of 2004.

    IOS infrastructure

    IOS Scheme Main Output Key Requirement Expected Completion Date
    St Pancras- Bedford Operational flexibility Ability for trains to cross between fast and slow lines at 50mph between Cricklewood and Radlett. 2004-05

    West Anglia Great Northern*

    West Anglia Route Modernisation
    The West Anglia route has seen considerable growth and is now capacity constrained. Renewal is in progress, and the section between Bethnal Green and Hackney Downs was recently completed. An enhancement programmes is being developed.

    Consultants have reported to the SRA on options for upgrading, for which the various economic cases are now being tested. The SRA is negotiating details of funding with BAA, whose Stansted Airport drives much of the West Anglia’s route’s projected traffic; traffic at the airport is rapidly expanding.

    The SRA has contracted with Railtrack for initial design and costing on certain options and for provision to be made for possible enhancement as renewals are carried out. The programme includes:

    • Four tracks Tottenham Hale – Brimsdown
    • Additional platforms and Liverpool Street station
    • Line speed improvements
    • Extended hours for services to Stansted Airport, and capacity enhancements at Stansted Airport station
    • Making signalling compatible with potential new rolling stock
    • Development of services to Stratford

    IOS stations – WAGN has 90 stations eligible for upgrades, works due to be completed by the end of 2004.

    RPP proposal

    RPP Proposal Status Output
    Finsbury Park Interchange pre-qualified expansion of the bus facility to improve interchange

    * See Eastern England briefing for details of WAGN developments in Hertfordshire, Cambridgeshire and Norfolk.

    Freight

    The main schemes affecting the South East are:

    Felixstowe-Nuneaton.

    The SRA intends to develop and implement the following:

    • Works to clear the route to W12 gauge, to permit use of 9ft 6in high deep sea containers\swap bodies and 9ft 6in high, 2.6m wide European intermodal units on 1,000mmm deck -height wagons throughout between the port of Felixstowe and the West Coast Main Line (WCML) at Nuneaton
    • Works to provide capacity sufficient to accommodate 30-40 freight trains per day in each direction by 2010,to meet projected demand between East Anglia and the Midlands\North

    Gauge and capacity improvements will help retain existing volumes of approximately 330,000 containers each year on rail to\from the port of Felixstowe (which would be progressively lost, as standard container heights increase to 9ft 6ins, without these improvements) and should absorb continuing growth in the deep sea and short sea intermodal markets. An additional benefit is the release of extra paths on the existing routes of the Great Eastern, north London Line and WCML south of Nuneaton for passenger and/or freight growth in these regions.

    Developments (2001-2002)

    • Feasibility work completed on W12 gauge clearance and capacity
    • Estimates for W12 gauge and capacity work on target for completion in early 2002.
    • Project implementation plan under development, in consultation with rail freight industry, to secure maximum early benefits from work o date; first physical project works to commence this year

    Developments (2001-2002)

    Output Expected Completion Date
    London diversionary route cleared to W10 gauge 2003-4
    Leicester-Nuneaton resignalling to provide improved signalling headways and layouts 9junctions and crossings) increase capacity and accommodate 775m trains 2003-4
    Full W10 gauge clearance on route 2004-5
    Full W12 gauge clearance 2005

    Developments (2005-2010)

    Output Expected Completion Date
    Full capacity enhancement completed 2010

    Southampton-West Midlands

    The upgrade of this route has as its objectives the ability to convey larger containers, retention and expansion of the current 35% market share for freight.

    Southampton is a key growth opportunity for rail. By 2010 the throughput of Southampton is projected to be 720,000 twenty foot equivalent units (TEU) per year and the new port proposed at Dibden Bay, if approved, would provide an additional throughput of some 1m TEUs per year. The expected completion date for full capacity enhancement of this route is 2009 with gauge clearance by 2005 and container length enhancement by 2006.

    North London and Great Eastern freight specific works

    The SRA intends to develop and implement the following:

    • W12 gauge clearance on the Great Eastern south of Ipswich and across North London (East-West), along with a diversionary route cleared to W10 gauge.

    These works should deliver a 50% increase over existing freight capacity across North London, and accommodate projected growth from Thameside ports and industry, and from possible developments at Bathside Bay and Shell Haven. Extra freight capacity on the Tottenham and Hampstead section will free passenger paths on the North London Line.

    To facilitate proposed increases in passenger services on the North London Line and through Stratford, most of the work involving the Barking -Willesden line will need to be completed in advance, to accommodate displaced freight flows.

    The benefits of this project are linked with the Felixstowe-Nuneaton project and, in particular, the linked clearance of Ipswich tunnel for longer vehicles: the freight trains using these lines will also require a proportion of the 42 paths south of Crewe to be delivered by WCRM, to provide viable through transits.

    Developments (2002-2002)

    • Feasibility work on W12 gauge clearance Great Eastern/Thameshaven-WCML via Tottenham and Hampstead (including Hampstead Tunnel) and North London Line
    • Feasibility work on W10 clearance of North London Line
    • Feasibility work on providing capability for heavier trains (to at least Route Availability 10 between Barking and Willesden via Tottenham and Hampstead

    Developments (2002-2005)

    Outputs Expected Completion Date
    W10 gauge clearance Thameshaven-Camden junction via Tilbury and North London Line 2003
    Route availability 10 clearance Woodgrange Park-Harlesden Junction (WCML) via Tottenham and Hampstead 2003
    Increased capacity by implementing improvements to signalling headways and junction speeds, Gospel Oak (from Tottenham and Hampstead)- Willesden Junction 2003
    Increased capacity by implementing improvements to signalling headways, Woodgrange Park-Gospel Oak 2004
    W10 clearance of the Great Eastern main Line: Stratford-Harwich and Ipswich (Halifax Junction) 2004
    W10 clearance Woodgrange Park-Harlesden Junction (WCML) via Tottenham and Hampstead 2005
    W12 clearance Woodgrange Park-Harlesden Junction (WCML) via Tottenham and Hampstead 2005

    Longer Term Schemes

    South London Metro

    The Mayor of London’s Transport Strategy states that Transport for London will work with other parties “to identify a phased programme, co-ordinated with franchise replacement, for the implementation of the London Metro concept, including Orbirail”. This aspiration to integrate national Rail more closely into London’s wider public transport network is particularly applicable South London, where there is limited Underground provision.

    The South London Metro concept aims to provide a ‘turn up and go’ high frequency service South of the Thames in the Greater London area.

    A Steering Group , chaired by the SRA, comprising the key stakeholders, including TfL, Railtrack, the TOCs, local authority and passengers representatives has been meeting regularly to take forward implementation.

    In the first instance, improvement in service provision is being secured through the replaced franchises for South West Trains and South Central and a possible extension of the Connex South Eastern franchise. In particular, higher frequency services in the off-peak, and refurbished rolling stock, will be delivered by South West Trains and South central as part of their franchise replacement programmes. A possibility in the South Eastern area is the acquisition of rolling stock specially designed for the high numbers of boardings and alightings characteristic of the Metro area.

    In the longer term, the South London Metro concept would require a major increase in service frequencies on many routes, which could ultimately only be achieved by reallocating capacity, or by new investment. The SRA expects to fund development work on the potential of a higher frequency South London Metro during the period of this Plan.

    London Crossrail

    Options for taking forward this scheme as well as the proposed Merton-Hackney project are being developed by the newly formed SRA-TfL joint venture, Cross London Rail Links, with SRA and TfL together providing £150m for project development.

    Several other schemes, such as the proposed High Speed Line, the Kings Cross Superhub and enhanced airport links will also provide benefits in the longer term for London and the South East. These will be further enhanced by the upgrade of the Great Western line and the ongoing outputs from the Network Management Statement.

  • HISTORIC PRESS RELEASE : Bowker Welcomes Huge South Central Trains Order [March 2002]

    HISTORIC PRESS RELEASE : Bowker Welcomes Huge South Central Trains Order [March 2002]

    The press release issued by the Strategic Rail Authority on 11 March 2002.

    Today’s announcement of GoVia’s order of a further 460 vehicles for its South Central franchise has been welcomed by SRA Chairman Richard Bowker. The number of new vehicles on order for South Central now totals 700.

    Speaking at the press launch in London today, he said:

    “This £850million deal shows the willingness and commitment of the private sector to invest in the railway. We have worked closely with GoVia on the arrangements, which are geared to meet the huge challenge of eliminating Mark 1 ‘slam door’ stock on this franchise by the end of 2004. The scale of the order will also enable South Central to use 100 vehicles specifically for lengthening trains, helping to achieve our strategic aim of reducing overcrowding on the intensive London commuting networks.

    “The deals are now in place for Mark 1 replacement on South West Trains and South Central, and we expect an announcement on Connex South Eastern replacements in the near future. The SRA will be working closely with the operators and Railtrack to ensure effective operational transition of the new rolling stock.”

  • HISTORIC PRESS RELEASE : Rail Authority Chairman Offers Vision and Funding for Cornwall [April 2002]

    HISTORIC PRESS RELEASE : Rail Authority Chairman Offers Vision and Funding for Cornwall [April 2002]

    The press release issued by the Strategic Rail Authority on 16 April 2002.

    Richard Bowker, Chairman of the Strategic Rail Authority (SRA), visited Cornwall today and offered both long-term vision and short-term delivery for rail services in the county.

    At a series of meetings with railway staff, business, and civic leaders on the first part of a two-day visit to the West Country, he spoke about his plans for major improvements to the railways both locally and nationally. Confirming the importance of West Country services to the rail network, he spoke of how the rail industry is finding new ways of working closely together to achieve short-term improvements for passengers.

    During his visit, the SRA Chairman confirmed funding for two passenger rail schemes in Cornwall. The improvements, being funded through the SRA’s Rail Passenger Partnership (RPP) scheme, involve a major upgrade to Penzance Station to improve transport integration, and the introduction of more trains on the Truro to Falmouth line. He also confirmed that the SRA is taking forward further assessment work on potential RPP funding to double the seven-mile single-track section of the Great Western Main Line between Probus and Burngullow at a cost of £11m.

    During his visit, Richard Bowker said:

    “Rail services in Cornwall are of national importance. The funding announced today underlines our commitment to this railway – right through to the end of the line at Penzance, where the station improvements will be a real community project. The next step will be to develop the business case for providing more capacity on the mainline between Truro and St Austell, which passed a major milestone with the pre-qualification of this scheme today.”

    Details of the successful RPP schemes follow:

    Penzance Interchange
    The SRA is providing £250,000 of RPP funding towards the scheme’s total cost of £769,000. The proposal includes remodelling the bus station, upgrading and refurbishing toilets, improving the car park (with provision for cycles, motor cycles and disabled drivers), and various access and environmental improvements.

    Cornwall County Council is contributing £395,000 to the scheme. Other contributors include the Countryside Agency (£30,000), South West Arts Board (£30,000), First Western National (£25,000) and Penwith District Council (£24,381). It is estimated that work will be completed in late 2002 with full operation in 2002/3.

    Truro to Falmouth
    The SRA is providing £64,000 worth of RPP funding (over three years) to provide for an all year round Sunday service on the route (service currently operates on just 10 summer Sundays). The funding is being matched by £67,000 of funding from other sources, namely Cornwall County Council (£30,000), Countryside Agency (£31,000) and the Truro-Falmouth Partnership (£6,000).

  • HISTORIC PRESS RELEASE : Rail Authority Chairman Announces Funding for Devon Rail Services [April 2002]

    HISTORIC PRESS RELEASE : Rail Authority Chairman Announces Funding for Devon Rail Services [April 2002]

    The press release issued by the Strategic Rail Authority on 17 April 2002.

    On a visit to Devon today, Richard Bowker, Chairman of the Strategic Rail Authority (SRA), announced funding for additional services on the County’s ‘Tarka Line’.

    The announcement comes on the second day of a visit to the West Country, in which he is meeting railway staff, business, and civic leaders to discuss rail services in this strategically important region.

    Two additional weekday trains in each direction from Exeter Central to Barnstaple will run from the Summer 2002 timetable, bringing the service level to eleven trains each way daily. The funding has been made available through the SRA’s Rail Passenger Partnership (RPP) scheme for an eighteen-month period.

    The SRA is providing £144,000 towards overall cost of £367,000. Further funding is being provided by Wessex Trains, the Countryside Agency, Devon County Council and the Tarka Line Working Party.

    Commenting on the funding, Richard Bowker said:

    “Today’s announcement confirms our willingness to invest in North Devon’s railway. It will be a boost for local businesses and tourism, and is a positive response to the views of passengers and Devon County Council. I know that Wessex Trains will be working hard with the community to attract more passengers to make these extra trains a permanent feature of the timetable.”

  • HISTORIC PRESS RELEASE : Statement on Potters Bar Derailment [May 2002]

    HISTORIC PRESS RELEASE : Statement on Potters Bar Derailment [May 2002]

    The press release issued by the Strategic Rail Authority on 10 May 2002.

    SRA Chairman Richard Bowker said:

    “Our thoughts and sympathy, shared by the whole of the rail industry, are with all those involved in this accident and their families. We pay tribute to the work of the emergency services, done so professionally.

    “It is important that the cause be identified, and that responses are made after calm reflection. The Health and Safety Executive will be undertaking an investigation and will present their preliminary findings to the Secretary of State for Transport as soon as practically possible”.

  • HISTORIC PRESS RELEASE : SRA Invites Bids for £400 million Rail Performance Fund [May 2002]

    HISTORIC PRESS RELEASE : SRA Invites Bids for £400 million Rail Performance Fund [May 2002]

    The press release issued by the Strategic Rail Authority on 14 May 2002.

    Britain’s railway industry has been invited to join forces with the SRA to co-fund small scale investments aimed at providing shorter-term and lasting improvements to the performance of passenger and freight services.

    Bidding guidance is being distributed to relevant industry operators and stakeholders for accelerated projects that can be completed within a year, and also for longer term development projects. The SRA’s Rail Performance Fund (RPF) is a partnership funding scheme. It has a total budget of £400 million over ten years and is open to applications from across the rail network. For the present time, a passenger franchise operator must act as the lead project sponsor. Each bid will be assessed on a case by case basis.

    Examples of investments that would qualify for RPF funding include rolling stock modifications to improve reliability of trains, such as upgraded componentry; track and signalling infrastructure, for example the provision of additional and upgraded infrastructure to improve reliability; systems and process improvements including enhanced IT processes and data logging services.

    Launching the SRA’s new bidding guidance today, SRA Chairman, Richard Bowker said:

    “The Rail Performance Fund will help to fulfil one of the SRA’s primary objectives of working with the rail industry to achieve substantial and lasting improvements in performance. This fund enables us to co-invest with rail companies in quick win schemes to deliver a better and more reliable service for passengers and freight. We have already had over 85 expressions of interest from the rail industry and expect them to convert into formal RPF bids now that the official guidance is out.

    “The fund will work alongside our existing, and already successful, Rail Passenger Partnership and Freight Facilities Grant schemes to make a noticeable difference to the service that the industry provides to its customers.”

    Notes to Editors

    1. Copies of the Rail Performance Fund Bidding Guidance can be viewed on the SRA website (address below).

    2. Schemes where preliminary interest in RPF co-funding has already been expressed include modifications to enhance rolling stock and IT systems plus additional and upgraded infrastructure.

    3. The RPF was first outlined in the SRA’s Strategic Plan (January 2002). The scheme provides funding for performance improvement projects that cannot be commercially funded by the private sector and third parties alone. The fund can also be used to accelerate the implementation of existing performance improvement projects.

    4. Applications for funding can be submitted by rail stakeholders, either as individuals or in consortia with others. Each RPF application will require a passenger franchise Train Operating Company as the lead sponsor. The application will be assessed on its deliverability and capacity to improve performance to the rail network and societal gains. At a later date, the fund may be extended to cover bids directly from Railtrack, ROSCO’s, non-franchised operators (like Heathrow Express) and local authorities and PTE’s.

    5. The Rail Performance Fund Bidding Guidance outlines the stages of the bidding process. The process is divided into two types of projects – accelerated projects that can be implemented within one year and development projects for which project development is less well advanced. RPF bid submissions will be appraised by the SRA. Successful bids will be recommended to the RPF Project Board for approval and a letter of offer will be issued. On award of the RPF payment, the SRA will monitor the delivery of the project against the contract to ensure that the objectives are met. The RPF Board will draw on experts across the SRA, as well as independent consultants.

    6. The SRA budget for RPF in the first financial year (2002/03) is £40 million. RPF funding first became available from 1 April 2002. The fund has been structured to permit maximum funding flexibility and there is no pre-determined benchmark. However, the SRA expects bidders to make a significant contribution to the capital funding.