Tag: Angus Robertson

  • Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Angus Robertson on 2014-06-26.

    To ask the Secretary of State for Defence, what quantitative criteria have been used to set to remote the risk probability of a collision involving a Tornado aircraft.

    Mr Philip Dunne

    Military Aviation Authority Regulatory Article 1210 defines categories for quantifying the likelihood of a risk as follows:

    “Likelihood is assessed with respect to the likelihood of the assessed consequence of a hazard. This is based on the likelihood of a single accident resulting in harm for a particular fleet. The appropriate category listed below must be used:
    a. Frequent: Likely to occur at least several times a year.
    b. Occasional: Likely to occur one or more times per year.
    c. Remote: Likely to occur one or more times in 10 years.
    d. Improbable: Unlikely to occur in 10 years.”

    A panel of suitably qualified and experienced persons from the Tornado Force calculated the risk likelihood for the Tornado risk register based on this definition.

  • Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Angus Robertson on 2014-06-26.

    To ask the Secretary of State for Defence, which contracts with his Department worth over £50 million are behind schedule owing to the failure of suppliers to deliver to an agreed schedule; and in the case of each such contract, who the suppliers were.

    Mr Philip Dunne

    The Ministry of Defence currently has around 400 open contracts with a total value of more than £50 million. Current performance related information on each contract is not held centrally and could be provided only at disproportionate cost.

  • Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Angus Robertson on 2014-06-26.

    To ask the Secretary of State for Defence, how much of the £1.2 billion underspend in his Department’s equipment budget in 2012-13 arose as a result of programme slippage; what programmes were behind schedule; and for what reason those programmes were behind schedule.

    Mr Philip Dunne

    Our analysis of the £1.2 billion underspend in 2012-13 in our equipment programme shows that it has been caused by a combination of factors, including better than expected outcomes from contract negotiations; budget being allocated for risks that did not materialise; and the impact of programme slippage against plans.

    A detailed analysis of programme slippage by programme is not currently available, but further work to improve our detailed understanding of variations against planned spending patterns and the implications for project costs in future years is nearing completion.

    Due to our improved financial discipline the Treasury have allowed us to carry over in-year underspends into our future year budgets. The last National Audit Office Major Projects Report showed an 88% reduction in overall project delays.

    We now have the assurance of a stable and well managed budget and confidence that defence programmes are affordable and deliverable.

  • Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Angus Robertson on 2014-06-04.

    To ask the Secretary of State for Defence, whether any RAF pilot has flown the Joint Strike Fighter B at (a) supersonic speeds, (b) above 18 degrees angle of attack and (c) past 4.5 g-force.

    Mr Philip Dunne

    The RAF test pilot at NAS Patuxent River routinely flies the Joint Strike Fighter B at supersonic speeds, above 18 degrees angle of attack and past 4.5 g-force.

  • Angus Robertson – 2014 Parliamentary Question to the Foreign and Commonwealth Office

    Angus Robertson – 2014 Parliamentary Question to the Foreign and Commonwealth Office

    The below Parliamentary question was asked by Angus Robertson on 2014-06-04.

    To ask the Secretary of State for Foreign and Commonwealth Affairs, what progress has been made towards negotiating a peaceful solution with Iran on the nuclear issue.

    Hugh Robertson

    The November interim agreement between the E3+3 and Iran was a significant first step to resolving the nuclear issue. It has created time to negotiate a comprehensive agreement. On this we are making progress although we are under no illusion about the difficulty of reaching a successful outcome. Talks resume on 16 June in Vienna, with the aim of reaching an agreement by the 20 July which is when the interim deal currently expires.

  • Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Angus Robertson on 2014-06-11.

    To ask the Secretary of State for Defence, for what reason the initial estimate of the additional costs of reverting to the fallback position of a hosting solution provided by Capita for the Recruiting Partnering Project increased from £47.7 million to £70 million; and who was responsible for these estimates.

    Anna Soubry

    My right hon. Friend the Secretary of State for Defence (Philip Hammond) set out on 14 January 2014 (Official Report, column 716) the cost of Capita providing a new Information Technology platform as part of the Recruiting Partnering Project. At the time, these costs were expected to be around £47.7 million directly linked to the change of hosting provision. Since this statement, the £47.7 million has reduced to £42.9 million.

    As previously stated by the Secretary of State on 14 January, there has been an additional cost of around £1 million per month to run the Capita system. This includes costs for additional manpower.

    The Recruiting Partnering Project remains within the overall agreed cost of £1.360 billion.

  • Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Angus Robertson on 2014-06-16.

    To ask the Secretary of State for Defence, what deviations or exemptions from the Military Air Systems Certifications Process were made for the Airseeker aircraft; when those deviations or exemptions were made; and who authorised each such deviation or exemption.

    Mr Philip Dunne

    I refer the hon. Member to the answer I gave on 16 June 2014, (Official Report, column 364W), to the hon. Member for Plymouth, Moor View (Alison Seabeck).

    Ongoing work will progressively refine this release as additional information becomes available and further analysis is conducted.

  • Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Angus Robertson on 2014-03-31.

    To ask the Secretary of State for Defence, with reference to paragraphs 7.22, 7.21 and 7.7 of Joint Service Publication 832, if he will place in the Library and on his Department’s website a copy of the Service inquiry regarding the collision of two Tornado aircraft over the Moray Firth on 3 July 2012.

    Dr Andrew Murrison

    I refer the hon. Member to the answer given by my right Hon. Friend the Minister of State for the Armed Forces (Mark Francois) on 3 December 2013, (Official Report, column 639W). It would be inappropriate to comment on any details relating to this incident prior to the publication of the Service Inquiry.

  • Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Angus Robertson on 2014-04-29.

    To ask the Secretary of State for Defence, what consideration his Department gave to procuring the Rangeless Airborne Instrumented Debriefing System with Collision Warning software for installation on the Tornado aircraft.

    Mr Philip Dunne

    The requirement of the Ministry of Defence was for an Instrument Debriefing System. Records of any consideration given to the procurement of additional capabilities are no longer centrally held and the retrieval of this information would be possible only at disproportionate cost.

  • Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    Angus Robertson – 2014 Parliamentary Question to the Ministry of Defence

    The below Parliamentary question was asked by Angus Robertson on 2014-06-04.

    To ask the Secretary of State for Defence, what estimate he has made of the total disposal cost of the Nimrod MRA4 airframes.

    Mr Philip Dunne

    The Nimrod MRA4 airframes were dismantled on the Ministry of Defence (MOD)’s behalf by Metal and Waste Recycling Ltd at a cost of around £500,000. As part of the contractual arrangements with the company, the MOD received receipts from the sale of the dismantled airframes to the value of just over £1 million.